Energy Projects Near You

Hallfield Farm, Easington Solar Farm (49.9 MW)

Hallfield Farm, Easington Solar Farm is a 49.9 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 12 July 2025, no decision recorded; the record was last updated on 29 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
29 August 2025record last updated
County Durhamcouncil area

Planning timeline

DateStage
12 July 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
29 August 2025
Operator or applicant
Eden Renewables
Planning authority
County Durham
Planning application reference
DM/25/01881/FPA
Site area
78.5 ha
Address (REPD)
Hallfield Farm Easington
Council area (by location)
County Durham
Name in REPD
Hallfield Farm, Easington - Solar Farm
REPD reference
18987

Recorded together with Hallfield Farm, Easington (57 MW battery storage, application submitted).

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carrs Farm, South Hettonbattery storage200application submitted1.5
Hawthorn Wind Farmwind farm7.5application withdrawn1.7
Woodlands, Windermere Roadbattery storage90application submitted1.8
Hawthorn Grid Sitebattery storage49operational1.8
Peterlee Solar Farmsolar farm5operational2.0
Hackworth Road, North West Industrial Estatesolar farm15.4application submitted2.3
Hawthorn Pit -Solar Farmsolar farm49.9approved, not built2.9
Fox Cover Solar Farm - Ground Mounted Photovoltaic Panelssolar farm8approved, not built3.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.793, -1.3702).