Energy Projects Near You

Hawthorn Wind Farm (7.5 MW)

Hawthorn Wind Farm is a 7.5 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 4 September 2008; the record was last updated on 13 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
application withdrawnstatus in REPD
13 September 2011record last updated
County Durhamcouncil area

Planning timeline

DateStage
30 April 2008Application submitted
4 September 2008Application withdrawn

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
application withdrawn
Record last updated
13 September 2011
Operator or applicant
SLP Energy
Planning authority
County Durham
Planning application reference
PLAN/2008/0319
Turbines
3
Address (REPD)
Is located between the villages of Hawthorn, Murton and Cold Hesledon
Council area (by location)
County Durham
REPD reference
3058

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hallfield Farm, Easingtonbattery storage57application submitted1.7
Hallfield Farm, Easington Solar Farmsolar farm49.9application submitted1.7
Hawthorn Grid Sitebattery storage49operational1.7
Woodlands, Windermere Roadbattery storage90application submitted1.7
Carrs Farm, South Hettonbattery storage200application submitted1.9
Hawthorn Pit -Solar Farmsolar farm49.9approved, not built2.2
Fox Cover Solar Farm - Ground Mounted Photovoltaic Panelssolar farm8approved, not built2.5
Peterlee Solar Farmsolar farm5operational3.6
Hackworth Road, North West Industrial Estatesolar farm15.4application submitted4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8079, -1.3707).