Energy Projects Near You

Hawthorn Pit Green Energy Park (1,000 MW)

Hawthorn Pit Green Energy Park is a 1,000 MW battery storage project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 August 2025, no decision recorded; the record was last updated on 28 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,000 MWbattery storage
application submittedstatus in REPD
28 October 2025record last updated
County Durhamcouncil area

Planning timeline

DateStage
27 August 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
1,000 MW
Status (REPD)
application submitted
Record last updated
28 October 2025
Operator or applicant
NatPower UK
Planning authority
County Durham
Planning application reference
DM/25/02255/FPA
Address (REPD)
The North West Of High Crows House Wheatley Hill
Council area (by location)
County Durham
Name in REPD
Hawthorn Pit Green Energy Park - Battery Energy Storage System
REPD reference
19676

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Edder Acres Farmwind farm5refused on appeal1.1
Haswell Moorwind farm10operational1.4
Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagesolar farm31.5refused1.6
Hackworth Road, North West Industrial Estatesolar farm15.4application submitted3.2
Peterlee Solar Farmsolar farm5operational3.5
Southern Lawwind farm5.2operational4.0
Trimdon Grangewind farm5.2operational4.4
Carrs Farm, South Hettonbattery storage200application submitted4.8
Hallfield Farm, Easingtonbattery storage57application submitted4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7538, -1.4052).