Energy Projects Near You

Solar Farm at E/O Stockton Road (48 MW)

Solar Farm at E/O Stockton Road is a 48 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 25 February 2025, no decision recorded; the record was last updated on 21 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWsolar farm
application submittedstatus in REPD
21 March 2025record last updated
County Durhamcouncil area

Planning timeline

DateStage
25 February 2025Application submitted

Project details

Technology
solar farm
Capacity
48 MW
Status (REPD)
application submitted
Record last updated
21 March 2025
Operator or applicant
Elements Green
Planning authority
County Durham
Planning application reference
DM/25/00287/FPA
Site area
81.6 ha
Address (REPD)
E/O Stockton Road, Seaham
Council area (by location)
County Durham
Name in REPD
Seaham Solar Park, Stockton Road - Solar Farm
REPD reference
17386

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
South Sharpley Wind Farm (Revised)wind farm7.5operational2.9
Fox Cover Solar Farm - Ground Mounted Photovoltaic Panelssolar farm8approved, not built4.4
Great Eppleton Farm Repoweringwind farm8.2operational5.1
Hawthorn Wind Farmwind farm7.5application withdrawn5.4
Hawthorn Pit -Solar Farmsolar farm49.9approved, not built5.7
Hastings Hill Farm, Foxcover Roadbattery storage38approved, not built6.1
Woodlands, Windermere Roadbattery storage90application submitted6.3
Hawthorn Grid Sitebattery storage49operational6.3
Fox Cover Roadbattery storage30approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8561, -1.3656).