Solar, wind and battery projects near Sunderland (SR1)
53 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SR1 (Sunderland): 6 are waiting for a planning decision, 35 approved but not yet running, 9 operational. The largest live scheme is West Boldon Substation (60 MW battery storage, approved on 10 December 2024, not yet built), 6.8 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 29.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SR1
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| E/o the Academy Of Light, Sunderland Road Solar Farmsolar farm | solar farm | 40 | application submitted may be out of dateupdated Jul 2024 | Jul 2024 | — | Jul 2024 | South Tyneside | 4.1 |
| Hastings Hill Farm, Foxcover Roadbattery storage | battery storage | 38 | approved, not builtupdated Aug 2025 | Oct 2024 | granted Jul 2025 | Aug 2025 | Sunderland | 5.1 |
| Calsonic Kanseirooftop solar | rooftop solar | 2.1 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Sunderland | 5.2 |
| Woodhouse Farmsolar farm | solar farm | 11 | refusedupdated Jan 2015 | Oct 2014 | refused Jan 2015 | Jan 2015 | Sunderland | 5.4 |
| Fox Cover Roadbattery storage | battery storage | 30 | approved, not builtupdated Oct 2024 | Sep 2023 | granted Sep 2024 | Oct 2024 | Sunderland | 5.6 |
| Solar Farm at E/O Stockton Roadsolar farm | solar farm | 48 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | County Durham | 5.6 |
| Washington Road Solar Farmsolar farm | solar farm | 20 | approved, not built may be out of dateupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | Sunderland | 5.9 |
| Nissan Test Tracksolar farm | solar farm | 4.8 | operationalupdated Jun 2016 | May 2015 | granted Jul 2015 | Jun 2016 | Sunderland | 5.9 |
| Nissan Wind Farm Extensionwind farm | wind farm | 4.3 | application withdrawnupdated Dec 2017 | Dec 2015 | — | Dec 2017 | Sunderland | 6.1 |
| Nissan Wind Farmwind farm | wind farm | 4 | operationalupdated Oct 2009 | Oct 2004 | granted Aug 2005 | Oct 2009 | Sunderland | 6.6 |
| Nissan Motors Plant Extnwind farm | wind farm | 2 | operationalupdated Nov 2013 | Jun 2007 | granted Jul 2007 | Nov 2013 | Sunderland | 6.6 |
| SNOP UK, Washington Roadrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Feb 2026 | Jan 2026 | granted Mar 2026 | Feb 2026 | Sunderland | 6.7 |
| West Boldon Substationbattery storage | battery storage | 60 | approved, not builtupdated Jul 2025 | Jul 2023 | granted Dec 2024 | Jul 2025 | South Tyneside | 6.8 |
| Unipres buildingrooftop solar | rooftop solar | 4.9 | operationalupdated Mar 2023 | Dec 2018 | granted Feb 2019 | Mar 2023 | Sunderland | 7.0 |
| South Sharpley Wind Farm (Revised)wind farm | wind farm | 7.5 | operationalupdated Jan 2013 | May 2008 | granted Apr 2011 | Jan 2013 | County Durham | 7.5 |
| High Sharpley Wind Farmwind farm | wind farm | 2.6 | operationalupdated Jul 2012 | Apr 2002 | granted Jun 2002 | Jul 2012 | County Durham | 7.8 |
| Salters Lanebattery storage | battery storage | 18 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | County Durham | 8.5 |
| Snop, Rainhill Roadrooftop solar | rooftop solar | 1.2 | approved, not built may be out of dateupdated May 2024 | Dec 2022 | granted Jan 2023 | May 2024 | Sunderland | 8.6 |
| Great Eppleton Farm Repoweringwind farm | wind farm | 8.2 | operationalupdated Jun 2011 | Mar 2007 | granted Aug 2007 | Jun 2011 | Sunderland | 9.3 |
| Great Eppleton Wind Farmwind farm | wind farm | 3 | operationalupdated Oct 2009 | Aug 1995 | granted Jul 1996 | Oct 2009 | Sunderland | 9.3 |
| Port of Tynebattery storage | battery storage | 35 | operationalupdated May 2019 | Sep 2016 | — | May 2019 | South Tyneside | 9.3 |
| NCL1, Follingsby Lanerooftop solar | rooftop solar | 3.9 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Gateshead | 9.6 |
| Fox Cover Solar Farm - Ground Mounted Photovoltaic Panelssolar farm | solar farm | 8 | approved, not builtupdated Jun 2025 | Mar 2024 | granted Mar 2025 | Jun 2025 | County Durham | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Saint Marys Car Park, Saint Marys Boulevardrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Feb 2023 | Jan 2022 | granted Feb 2023 | Feb 2023 | Sunderland | 0.5 |
| Saint Marys Car Park, Saint Marys Boulevardbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2023 | Jan 2022 | granted Feb 2023 | Feb 2023 | Sunderland | 0.5 |
| University Of Sunderland, Saint Peters Gaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Sunderland | 0.7 |
| University Of Sunderland Reg Vardy Centre, Liberty Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Sunderland | 0.8 |
| University of Sunderlandrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2022 | Apr 2022 | granted Jun 2022 | Apr 2022 | Sunderland | 0.9 |
| Buzz Bingo, Pallion New Roadrooftop solar | rooftop solar | — | application submitted | May 2026 | — | — | Sunderland | 2.0 |
| Sunderland City Council Independent Living Centrerooftop solar | rooftop solar | 0.2 | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Sunderland | 2.9 |
| Clearly Drinks, Riverside Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Sunderland | 3.0 |
| Venerable Bede Church Of England Academyrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Oct 2025 | Jan 2026 | Sunderland | 3.5 |
| Morrisons, Doxford Parkrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2025 | Mar 2025 | granted May 2025 | Jul 2025 | Sunderland | 5.1 |
| Marelli, Home Furniture Shoprooftop solar | rooftop solar | 1 | application withdrawnupdated Sep 2023 | Jun 2023 | — | Sep 2023 | Sunderland | 5.2 |
| Faltec, International Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Sunderland | 6.6 |
| Vantec, Turbine Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Sunderland | 7.0 |
| AESC UK, Giga Factories, Plot 2 - Plant 3, Warehouse, Office & Sub-stationsbattery storage | battery storage | — | approved, not builtupdated May 2026 | Apr 2024 | granted Apr 2026 | May 2026 | South Tyneside | 7.2 |
| Griffiths Textiles Machines, Alston Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Sep 2022 | Oct 2022 | Sunderland | 7.5 |
| Vantec, Infiniti Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Sunderland | 7.7 |
| Spire Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Sunderland | 7.9 |
| Stephenson Industrial Estate, Rutherford Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Sunderland | 8.7 |
| Encore Envelopes Limited, Industrial Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Sunderland | 8.8 |
| Middlefields Depot, Middlefields Industrial Estaterooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | South Tyneside | 8.8 |
| Mortimer community college, Reading Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 9.0 |
| Merchant House Warehouse, Tyne Dock Solar Photovoltaics Equipmentrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Sep 2023 | granted Nov 2023 | Dec 2023 | South Tyneside | 9.2 |
| Port Of Tyne, Tyne Dockbattery storage | battery storage | — | application submitted may be out of dateupdated Aug 2022 | Jul 2022 | — | Aug 2022 | South Tyneside | 9.3 |
| Simonside Industrial Unit, Shaftesbury Avenuerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | South Tyneside | 9.4 |
| Stephenson Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Sunderland | 9.4 |
| UTS Engineering, Pilgrimswayrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | South Tyneside | 9.5 |
| Sedgeletch Sewage Treatment Workssolar farm | solar farm | — | under constructionupdated Oct 2022 | Nov 2020 | granted Jan 2021 | Oct 2022 | Sunderland | 9.7 |
| Washington Primary Care Centre, Parkwayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Sunderland | 9.7 |
| Lighthouse View Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | County Durham | 9.9 |
| The Galleries, Washington Town Centrerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | Sunderland | 9.9 |
Distance from the average position of the SR1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 2 | 3 | 1 | 1 | 116 |
| Rooftop solar | 30 | 2 | 26 | 1 | 0 | 16.9 |
| Wind farm | 7 | 0 | 0 | 6 | 0 | 0 |
| Battery storage | 9 | 2 | 6 | 1 | 0 | 146 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 29.0 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 29.0 |
| Teesside Offshore Wind Farm | 62 | operationalupdated May 2015 | 34.2 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Sunderland decides solar, wind and battery applications
| Applications | Sunderland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 3 (8%) | 19% |
| Solar refused | 3 of 31 | 12% |
| Onshore wind refused | 0 of 4 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 8.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SR1, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.