Washington Road Solar Farm (20 MW)

Washington Road Solar Farm is a 20 MW solar farm project in Sunderland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 December 2021, not yet built; the record was last updated on 8 December 2021. REPD also records that the planning permission expired on 1 December 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtmay be out of datestatus in REPD
8 December 2021record last updated
Sunderlandcouncil area

REPD also records that the planning permission expired on 1 December 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
8 October 2021Application submitted
1 December 2021Planning permission granted
1 December 2024Permission expired

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
8 December 2021
Operator or applicant
Engerera Renewables Limited
Planning authority
Sunderland
Planning application reference
21/02381/FUL
Site area
18.4 ha
Address (REPD)
Nissan Motor Manufacturing Uk Limited, Washington Road, Usworth, Sunderland
Council area (by location)
Sunderland
Time to decision
8 weeks
Name in REPD
Washington Road - Solar Farm
REPD reference
9841

Who decides

ApplicationsSunderlandUK
Decided applications (solar, wind, battery)4010,236
Refused3 (8%)19%
Solar refused3 of 3112%
Onshore wind refused0 of 445%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodhouse Farmsolar farm11refused1.7
West Boldon Substationbattery storage60approved, not built2.0
Fox Cover Roadbattery storage30approved, not built3.9
Hastings Hill Farm, Foxcover Roadbattery storage38approved, not built4.2
Usworth House Farm, Peareth Hall Road Solar Farmsolar farm27.3refused5.3
E/o the Academy Of Light, Sunderland Road Solar Farmsolar farm40application submitted5.3
Port of Tynebattery storage35operational6.3
Church Bankbattery storage100application submitted6.5
Mary Avenue, Birtleybattery storage71refused7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9206, -1.4669).