Mary Avenue, Birtley (71 MW battery storage)

Mary Avenue, Birtley is a 71 MW battery storage project in Gateshead, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 20 January 2026; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

71 MWbattery storage
refusedstatus in REPD
10 February 2026record last updated
Gatesheadcouncil area

Planning timeline

DateStage
26 June 2024Application submitted
20 January 2026Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
71 MW
Status (REPD)
refused
Record last updated
10 February 2026
Operator or applicant
Fig Power
Planning authority
Gateshead
Planning application reference
DC/24/00258/FUL
Address (REPD)
Mary Avenue Birtley
Council area (by location)
Gateshead
Time to decision
82 weeks
Name in REPD
Mary Avenue, Birtley - Battery Energy Storage
REPD reference
16187

Who decides

ApplicationsGatesheadUK
Decided applications (solar, wind, battery)2310,236
Refused1 (4%)19%
Solar refused0 of 2012%
Battery storage refused1 of 316%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Usworth House Farm, Peareth Hall Road Solar Farmsolar farm27.3refused3.5
Morris Marble Works, Cross Lanebattery storage100application withdrawn7.9
Washington Road Solar Farmsolar farm20approved, not built7.9
Woodhouse Farmsolar farm11refused7.9
Fox Cover Roadbattery storage30approved, not built8.3
West Boldon Substationbattery storage60approved, not built8.7
Hastings Hill Farm, Foxcover Roadbattery storage38approved, not built9.0
Wagtail Lane, Cragheadsolar farm27refused9.2
Land at Derwenthaugh Eco Parkbattery storage29permission expired9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9002, -1.5856).