Energy Projects Near You

Morris Marble Works, Cross Lane (100 MW battery storage)

Morris Marble Works, Cross Lane is a 100 MW battery storage project in Gateshead, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 4 December 2025; the record was last updated on 16 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
application withdrawnstatus in REPD
16 December 2025record last updated
Gatesheadcouncil area

Planning timeline

DateStage
23 July 2025Application submitted
4 December 2025Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
application withdrawn
Record last updated
16 December 2025
Operator or applicant
Bluefield Renewable Developments Limited
Planning authority
Gateshead
Planning application reference
DC/25/00366/FUL
Address (REPD)
Adj Morris Marble Works, East Side Of Cross Lane, Gateshead
Council area (by location)
Gateshead
Name in REPD
Morris Marble Works, Cross Lane - Battery Energy Storage
REPD reference
19439

Who decides

ApplicationsGatesheadUK
Decided applications (solar, wind, battery)2310,236
Refused1 (4%)19%
Solar refused0 of 2012%
Battery storage refused1 of 316%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Derwenthaugh Eco Parkbattery storage29permission expired2.0
Newburn BESSbattery storage90application submitted5.5
Newburn Bridge Roadbattery storage100approved, not built5.5
Mary Avenue, Birtleybattery storage71refused7.9
Usworth House Farm, Peareth Hall Road Solar Farmsolar farm27.3refused8.0
Benton Lane, Quorum Business Parksolar farm8application submitted8.7
Newcastle International Airport Phase 3- Solar Farmsolar farm5approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9571, -1.6599).