Solar, wind and battery projects near Blaydon-on-Tyne (NE21)
67 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE21 (Gateshead): 5 are waiting for a planning decision, 56 approved but not yet running, 1 operational. The largest live scheme is Newburn Bridge Road (100 MW battery storage, approved on 31 March 2022, not yet built; REPD status may be out of date), 2.3 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 32.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE21
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Land at Derwenthaugh Eco Parkbattery storage | battery storage | 29 | permission expiredupdated May 2020 | Mar 2018 | granted Nov 2018 | May 2020 | Gateshead | 2.2 |
| Newburn Bridge Roadbattery storage | battery storage | 100 | approved, not built may be out of dateupdated Oct 2024 | Aug 2021 | granted Mar 2022 | Oct 2024 | Gateshead | 2.3 |
| Newburn BESSbattery storage | battery storage | 90 | application submitted may be out of dateupdated Jul 2024 | May 2024 | — | Jul 2024 | Newcastle upon Tyne | 2.8 |
| Morris Marble Works, Cross Lanebattery storage | battery storage | 100 | application withdrawnupdated Dec 2025 | Jul 2025 | — | Dec 2025 | Gateshead | 3.9 |
| Parker Hannifin Manufacturingrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Gateshead | 6.7 |
| Responsive Engineering, Scotswood Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle upon Tyne | 6.9 |
| Greenhead Energy Parksolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Gateshead | 7.9 |
| Greenhead Energy Parkbattery storage | battery storage | 13 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Gateshead | 7.9 |
| Albany Roadsolar farm | solar farm | 2 | approved, not built may be out of dateupdated Dec 2022 | Oct 2021 | granted Dec 2021 | Dec 2022 | Gateshead | 8.4 |
| Comeleon House Solar PV Farmsolar farm | solar farm | 4 | abandonedupdated Jun 2016 | May 2015 | granted Jun 2015 | Jun 2016 | County Durham | 8.4 |
| Newcastle International Airport Phase 3- Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 9.0 |
| Newcastle International Airport Phase 2 Solar Farmsolar farm | solar farm | 4 | approved, not built may be out of dateupdated Oct 2021 | Sep 2021 | granted Feb 2022 | Oct 2021 | Newcastle upon Tyne | 9.0 |
| Newcastle International Airport Phase 4 Solar Farmsolar farm | solar farm | 4 | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 9.0 |
| Newcastle International Airport Phase 1 -Solar Farmsolar farm | solar farm | 3 | under constructionupdated Oct 2021 | Sep 2021 | granted Mar 2022 | Oct 2021 | Newcastle upon Tyne | 9.0 |
Smaller schemes under 1 MW, mostly rooftop solar (53)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Gas Governor Station Solar Systemsolar farm | solar farm | 0.3 | approved, not built may be out of dateupdated Jan 2022 | Nov 2020 | granted Apr 2022 | Jan 2022 | Gateshead | 1.8 |
| Newburn Haugh Battery Storage Systemcbattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jun 2025 | Jul 2025 | Newcastle upon Tyne | 1.8 |
| Bailey House, Stargate Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 | Gateshead | 2.1 |
| Warburtons, Shelley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle upon Tyne | 2.3 |
| Union Hall Road, Lemingtonbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2023 | Aug 2022 | granted Jan 2023 | Feb 2023 | Newcastle upon Tyne | 2.4 |
| Shelley Roadbattery storage | battery storage | — | refusedupdated Nov 2018 | Oct 2017 | refused Dec 2017 | Nov 2018 | Newcastle upon Tyne | 2.4 |
| Excelsior Academy, Denton Roadrooftop solar | rooftop solar | 0.5 | under constructionupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 2.7 |
| Metrocentre, St Michaels Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Gateshead | 3.4 |
| Metrocentre Green Car Park, St Michaels Way - Photovoltaic Equipmentsolar farm | solar farm | — | under constructionupdated Sep 2022 | Dec 2021 | granted Jan 2023 | Sep 2022 | Gateshead | 3.5 |
| Paradise Works, Scotswood Road - Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Newcastle upon Tyne | 3.7 |
| Hadrian School, Bertram Crescentrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 4.1 |
| West Denton Leisure Centre - Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2021 | Aug 2021 | granted Sep 2021 | Sep 2021 | Newcastle upon Tyne | 4.3 |
| Canning Street Primary School - Photovoltaic Panelsrooftop solar | rooftop solar | — | approved, not builtupdated May 2021 | Apr 2021 | granted Jun 2021 | May 2021 | Newcastle upon Tyne | 4.4 |
| West Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2021 | Aug 2021 | granted Sep 2021 | Sep 2021 | Newcastle upon Tyne | 4.5 |
| Walbottle Campus Technology Collegerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2021 | Apr 2021 | granted Jun 2021 | Sep 2021 | Newcastle upon Tyne | 4.6 |
| Dunston Leisure Centre, Dunston Bankrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Jan 2025 | granted Apr 2025 | May 2025 | Gateshead | 4.7 |
| Stamfordham Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2021 | Aug 2021 | granted Oct 2021 | Oct 2021 | Newcastle upon Tyne | 5.2 |
| Sanderson Street - Photovoltaic panelsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Dec 2023 | Jan 2024 | Newcastle upon Tyne | 5.2 |
| Arnold Clark Seat & Body Shop, Gardener Streetrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Newcastle upon Tyne | 5.4 |
| Monkhouse And Brown, Team Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Gateshead | 5.6 |
| Dacon Fabrications Limited, Dukeswayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Gateshead | 6.7 |
| Newcastle University Sports Centrerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Newcastle upon Tyne | 6.7 |
| Dame Margaret Barbour Building - Photovoltaic panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2021 | Jun 2021 | granted Aug 2021 | Jun 2021 | Newcastle upon Tyne | 6.8 |
| Riverdale Paper, Earlswayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Gateshead | 6.8 |
| The Kenton Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Dec 2023 | granted May 2024 | May 2024 | Newcastle upon Tyne | 6.9 |
| Newcastle University, Boiler House - Roof Mounted Photovoltaic Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Aug 2023 | Jul 2023 | granted Aug 2023 | Aug 2023 | Newcastle upon Tyne | 7.1 |
| Students Union Buildingrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2022 | Feb 2022 | granted Apr 2022 | Feb 2022 | Newcastle upon Tyne | 7.2 |
| Team Valley Trading Estate Solar Photovoltaic Equipmentrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 | Gateshead | 7.3 |
| Newcastle University, Robinson Libraryrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 | Newcastle upon Tyne | 7.5 |
| Salem Tubes, Regents Drive Solar PV Equipmentrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Northumberland | 7.5 |
| Regent Streetsolar farm | solar farm | — | operationalupdated Nov 2023 | Jun 2021 | granted Sep 2021 | Nov 2023 | Gateshead | 7.6 |
| Royal Grammar School, Eskdale Terracerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Newcastle upon Tyne | 7.8 |
| Saint Nicholas Hospital, Jubilee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle upon Tyne | 7.8 |
| Welford Day Centre, Jubilee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Aug 2023 | Oct 2023 | Newcastle upon Tyne | 8.0 |
| Newington Road West Depotrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Dec 2021 | granted Feb 2022 | Feb 2022 | Newcastle upon Tyne | 8.4 |
| Ouseburn Trust, Lime Street Solar Panels & ASHPsrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Newcastle upon Tyne | 8.5 |
| South Causey Inn, Causey Roadsolar farm | solar farm | 0.2 | refusedupdated Mar 2024 | Sep 2023 | refused Mar 2024 | Mar 2024 | County Durham | 8.5 |
| Grange First School, Norham Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 8.6 |
| Gosforth Academy, Knightsbridgerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Sep 2023 | Oct 2023 | Newcastle upon Tyne | 8.8 |
| Gosforth Academyrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Newcastle upon Tyne | 8.8 |
| Neilson Roadsolar farm | solar farm | 0.9 | approved, not built may be out of dateupdated Feb 2022 | Oct 2021 | granted Dec 2021 | Feb 2022 | Gateshead | 9.0 |
| Newcastle International Airport Phase 2battery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 9.0 |
| Newcastle International Airport Phase 3battery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 9.0 |
| Newcastle International Airport Phase 4battery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 9.0 |
| David Lloyd Leisure, Castles Farm Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Newcastle upon Tyne | 9.2 |
| Queen Elizabeth Avenue, Sheriff Hill Solar Arraysrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Gateshead | 9.2 |
| Hadrian Square - Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2021 | Aug 2021 | granted Sep 2021 | Oct 2021 | Newcastle upon Tyne | 9.4 |
| Harelaw Industrial Estaterooftop solar | rooftop solar | 0.9 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Oct 2023 | Oct 2023 | County Durham | 9.5 |
| Brunton First School, Roseden Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 9.5 |
| Robert Duncan Timber Limited, Green Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Jan 2023 | Feb 2023 | Gateshead | 9.6 |
| YHN House, Benton Park Road- Solar Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Dec 2021 | Jan 2022 | Newcastle upon Tyne | 9.7 |
| Ponteland Community Primary School, Callerton Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Northumberland | 9.7 |
| Ravenswood Primary School, Ravenswood Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 9.9 |
Distance from the average position of the NE21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 1 | 8 | 1 | 1 | 69.1 |
| Rooftop solar | 44 | 2 | 42 | 0 | 0 | 15.1 |
| Battery storage | 11 | 2 | 6 | 0 | 1 | 203 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 32.5 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 32.5 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Gateshead decides solar, wind and battery applications
| Applications | Gateshead | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 1 (4%) | 19% |
| Solar refused | 0 of 20 | 12% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE21, 15 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.