Solar, wind and battery projects near Hebburn (NE31)
114 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE31 (South Tyneside): 9 are waiting for a planning decision, 89 approved but not yet running, 7 operational. The largest live scheme is Church Bank (100 MW battery storage, application submitted on 5 September 2025, no decision recorded), 2.8 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 23.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE31
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| A&P Tynewind turbine | wind turbine | 2 | permission expiredupdated Jun 2015 | Feb 2008 | granted Apr 2009 | Jun 2015 | South Tyneside | 1.6 |
| Church Bankbattery storage | battery storage | 100 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | South Tyneside | 2.8 |
| Port of Tynebattery storage | battery storage | 35 | operationalupdated May 2019 | Sep 2016 | — | May 2019 | South Tyneside | 3.7 |
| NCL1, Follingsby Lanerooftop solar | rooftop solar | 3.9 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Gateshead | 3.8 |
| Standby Embedded Stor Power Plantbattery storage | battery storage | 20 | under constructionupdated Jan 2023 | Apr 2021 | granted Jun 2021 | Jan 2023 | North Tyneside | 4.2 |
| West Boldon Substationbattery storage | battery storage | 60 | approved, not builtupdated Jul 2025 | Jul 2023 | granted Dec 2024 | Jul 2025 | South Tyneside | 4.6 |
| Albany Roadsolar farm | solar farm | 2 | approved, not built may be out of dateupdated Dec 2022 | Oct 2021 | granted Dec 2021 | Dec 2022 | Gateshead | 5.0 |
| SNOP UK, Washington Roadrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Feb 2026 | Jan 2026 | granted Mar 2026 | Feb 2026 | Sunderland | 5.6 |
| Usworth House Farm, Peareth Hall Road Solar Farmsolar farm | solar farm | 27.3 | refusedupdated Dec 2025 | Jan 2023 | refused Oct 2025 | Dec 2025 | Sunderland | 5.7 |
| Snop, Rainhill Roadrooftop solar | rooftop solar | 1.2 | approved, not built may be out of dateupdated May 2024 | Dec 2022 | granted Jan 2023 | May 2024 | Sunderland | 5.7 |
| Unipres buildingrooftop solar | rooftop solar | 4.9 | operationalupdated Mar 2023 | Dec 2018 | granted Feb 2019 | Mar 2023 | Sunderland | 6.1 |
| Tynemouth Energy Storage System (TESS)battery storage | battery storage | 25 | operationalupdated Aug 2018 | Sep 2016 | — | Aug 2018 | North Tyneside | 6.2 |
| Washington Road Solar Farmsolar farm | solar farm | 20 | approved, not built may be out of dateupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | Sunderland | 6.3 |
| Nissan Test Tracksolar farm | solar farm | 4.8 | operationalupdated Jun 2016 | May 2015 | granted Jul 2015 | Jun 2016 | Sunderland | 6.3 |
| Responsive Engineering, Scotswood Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle upon Tyne | 6.5 |
| Nissan Wind Farmwind farm | wind farm | 4 | operationalupdated Oct 2009 | Oct 2004 | granted Aug 2005 | Oct 2009 | Sunderland | 6.7 |
| Nissan Motors Plant Extnwind farm | wind farm | 2 | operationalupdated Nov 2013 | Jun 2007 | granted Jul 2007 | Nov 2013 | Sunderland | 6.7 |
| Nissan Wind Farm Extensionwind farm | wind farm | 4.3 | application withdrawnupdated Dec 2017 | Dec 2015 | — | Dec 2017 | Sunderland | 6.9 |
| Benton Lane, Quorum Business Parksolar farm | solar farm | 8 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Tyneside | 7.2 |
| Woodhouse Farmsolar farm | solar farm | 11 | refusedupdated Jan 2015 | Oct 2014 | refused Jan 2015 | Jan 2015 | Sunderland | 8.0 |
| E/o the Academy Of Light, Sunderland Road Solar Farmsolar farm | solar farm | 40 | application submitted may be out of dateupdated Jul 2024 | Jul 2024 | — | Jul 2024 | South Tyneside | 8.3 |
| Parker Hannifin Manufacturingrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Gateshead | 8.4 |
| Backworth Lane, Backworth Solar Farmsolar farm | solar farm | 28 | approved, not built may be out of dateupdated Oct 2024 | Nov 2022 | granted May 2023 | Oct 2024 | North Tyneside | 8.4 |
| Mary Avenue, Birtleybattery storage | battery storage | 71 | refusedupdated Feb 2026 | Jun 2024 | refused Jan 2026 | Feb 2026 | Gateshead | 9.1 |
| Mylord Crescent, Camperdown Industrial Estate, Unit 12rooftop solar | rooftop solar | 1.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | North Tyneside | 9.4 |
| Morris Marble Works, Cross Lanebattery storage | battery storage | 100 | application withdrawnupdated Dec 2025 | Jul 2025 | — | Dec 2025 | Gateshead | 9.5 |
| Calsonic Kanseirooftop solar | rooftop solar | 2.1 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Sunderland | 9.6 |
| Komatsu UK, Durham Roadrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Feb 2025 | Oct 2024 | granted Dec 2024 | Feb 2025 | Gateshead | 9.9 |
| Rolls Royce Plc, Radial Park Roadrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Sunderland | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (60)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hebburn Lakes Primary School, Campbell Park Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 0.3 |
| Clarendon, Windmill Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | South Tyneside | 1.5 |
| Viking Energy Network, Blackett Street - Turbine Repoweringwind turbine | wind turbine | 0.8 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | South Tyneside | 1.6 |
| Tyneview Primary School, Winslow Placerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 1.8 |
| Unit 1, Walker Riverside, Wincomblee Road -Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Newcastle upon Tyne | 1.9 |
| Soil Machine Dynamic, Davy Bankrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Feb 2024 | granted Feb 2024 | Mar 2024 | North Tyneside | 2.1 |
| Donwood Double Glazing, Stonehills Buildings - Unit A23 - Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Gateshead | 2.3 |
| Walker Riverside Academy - Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2021 | Apr 2021 | granted Jun 2021 | Jun 2021 | Newcastle upon Tyne | 2.3 |
| Simonside Industrial Unit, Shaftesbury Avenuerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | South Tyneside | 2.9 |
| Walkergate Primary School - Photovoltaic Panelsrooftop solar | rooftop solar | — | approved, not builtupdated May 2021 | Apr 2021 | granted Jun 2021 | May 2021 | Newcastle upon Tyne | 3.3 |
| UTS Engineering, Pilgrimswayrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | South Tyneside | 3.4 |
| Big Yellow Self Storagerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Gateshead | 3.5 |
| Benfield Business Park, Benfield Road -Solar Panelsrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Jul 2024 | Aug 2024 | Newcastle upon Tyne | 3.6 |
| Benfield School, Benfield Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 3.6 |
| Benfield School, Benfield Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 3.6 |
| Port Of Tyne, Tyne Dockbattery storage | battery storage | — | application submitted may be out of dateupdated Aug 2022 | Jul 2022 | — | Aug 2022 | South Tyneside | 3.7 |
| Robert Duncan Timber Limited, Green Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Jan 2023 | Feb 2023 | Gateshead | 3.9 |
| Venus Park, Trading Estatebattery storage | battery storage | — | approved, not builtupdated Mar 2024 | Jul 2022 | granted Sep 2022 | Mar 2024 | North Tyneside | 4.1 |
| Armadillo Self Storage, Heatonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Newcastle upon Tyne | 4.1 |
| Hadrian Square - Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2021 | Aug 2021 | granted Sep 2021 | Oct 2021 | Newcastle upon Tyne | 4.2 |
| Merchant House Warehouse, Tyne Dock Solar Photovoltaics Equipmentrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Sep 2023 | granted Nov 2023 | Dec 2023 | South Tyneside | 4.2 |
| Hamar Close & Wallsend Road, High Flatworthbattery storage | battery storage | — | approved, not builtupdated Oct 2024 | Apr 2023 | granted Sep 2024 | Oct 2024 | North Tyneside | 4.2 |
| Middlefields Depot, Middlefields Industrial Estaterooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | South Tyneside | 4.4 |
| Neilson Roadsolar farm | solar farm | 0.9 | approved, not built may be out of dateupdated Feb 2022 | Oct 2021 | granted Dec 2021 | Feb 2022 | Gateshead | 4.5 |
| Border Control Post, Coble Denerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | North Tyneside | 4.6 |
| Ravenswood Primary School, Ravenswood Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 4.7 |
| AESC UK, Giga Factories, Plot 2 - Plant 3, Warehouse, Office & Sub-stationsbattery storage | battery storage | — | approved, not builtupdated May 2026 | Apr 2024 | granted Apr 2026 | May 2026 | South Tyneside | 4.9 |
| Ouseburn Trust, Lime Street Solar Panels & ASHPsrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Newcastle upon Tyne | 5.1 |
| Stephenson Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Sunderland | 5.1 |
| Newington Road West Depotrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Dec 2021 | granted Feb 2022 | Feb 2022 | Newcastle upon Tyne | 5.4 |
| Faltec, International Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Sunderland | 5.5 |
| Stephenson Industrial Estate, Rutherford Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Sunderland | 5.6 |
| Queen Elizabeth Avenue, Sheriff Hill Solar Arraysrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Gateshead | 5.7 |
| Mortimer community college, Reading Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 5.7 |
| Corchester Walk Solar Photovoltaic Panels & Air Sourced Heat Pumpsrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted May 2022 | Jan 2022 | Newcastle upon Tyne | 5.7 |
| Regent Streetsolar farm | solar farm | — | operationalupdated Nov 2023 | Jun 2021 | granted Sep 2021 | Nov 2023 | Gateshead | 5.9 |
| Unit B, Merlin Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | North Tyneside | 6.0 |
| Unit C, Merlin Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Tyneside | 6.0 |
| Unit A, Merlin Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Tyneside | 6.1 |
| Vantec, Turbine Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Sunderland | 6.1 |
| Royal Grammar School, Eskdale Terracerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Newcastle upon Tyne | 6.2 |
| Tynemouth Substationbattery storage | battery storage | — | application withdrawnupdated May 2026 | Aug 2024 | — | May 2026 | North Tyneside | 6.2 |
| Newcastle University, Robinson Libraryrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 | Newcastle upon Tyne | 6.4 |
| David Lloyd Leisure, Castles Farm Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Newcastle upon Tyne | 6.5 |
| Students Union Buildingrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2022 | Feb 2022 | granted Apr 2022 | Feb 2022 | Newcastle upon Tyne | 6.6 |
| Westoe Crown Primary School, Sea Winnings Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 6.6 |
| Newcastle University, Boiler House - Roof Mounted Photovoltaic Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Aug 2023 | Jul 2023 | granted Aug 2023 | Aug 2023 | Newcastle upon Tyne | 6.6 |
| Whitley Road, Holystonebattery storage | battery storage | — | application withdrawnupdated Jun 2026 | Aug 2022 | — | Jun 2026 | North Tyneside | 6.6 |
| North Tyneside General Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | North Tyneside | 6.7 |
| Encore Envelopes Limited, Industrial Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Sunderland | 6.8 |
| YHN House, Benton Park Road- Solar Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Dec 2021 | Jan 2022 | Newcastle upon Tyne | 6.9 |
| Spire Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Sunderland | 6.9 |
| Vantec, Infiniti Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Sunderland | 7.0 |
| Quorum Building, Benton Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | North Tyneside | 7.0 |
| Dunes Amusement Arcade, Sea Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | South Tyneside | 7.0 |
| Dame Margaret Barbour Building - Photovoltaic panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2021 | Jun 2021 | granted Aug 2021 | Jun 2021 | Newcastle upon Tyne | 7.2 |
| Riverdale Paper, Earlswayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Gateshead | 7.4 |
| Newcastle University Sports Centrerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Newcastle upon Tyne | 7.4 |
| Planet Place, Stephenson Industrial Estate - Unit 27 - Battery Energy Storagebattery storage | battery storage | — | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | North Tyneside | 7.6 |
| Griffiths Textiles Machines, Alston Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Sep 2022 | Oct 2022 | Sunderland | 7.7 |
25 more projects not listed (furthest or smallest).
Distance from the average position of the NE31 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 2 | 4 | 2 | 2 | 98.9 |
| Rooftop solar | 84 | 3 | 79 | 1 | 0 | 38.5 |
| Wind farm | 3 | 0 | 0 | 2 | 0 | 0 |
| Wind turbine | 2 | 1 | 0 | 0 | 0 | 0.8 |
| Battery storage | 15 | 3 | 6 | 2 | 1 | 180 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 23.8 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 23.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How South Tyneside decides solar, wind and battery applications
| Applications | South Tyneside | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 12 | 10,236 |
| Refused | 1 (8%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 6.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in South Tyneside
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE31, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.