Energy Projects Near You

Renewable energy projects in South Tyneside

17 solar, wind or battery projects of 150 kW or more are located in South Tyneside (REPD, July 2026 extract): 4 pending, 11 approved but not running, 1 operational and 0 refused. The council refused 1 of 12 decided applications (8%; UK 19%), with a median 6 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects in the council area
4awaiting a decision
11approved, not running
8%of decisions refused

How South Tyneside decides

ApplicationsSouth TynesideUK
Decided applications (solar, wind, battery)1210,236
Refused1 (8%)19%
Solar refused0 of 912%
Onshore wind refused0 of 145%
Battery storage refused1 of 216%
Median time from submission to decision6.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in South Tyneside

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Church Bankbattery storagebattery storage100application submittedupdated Oct 2025Sep 2025—Oct 2025
West Boldon Substationbattery storagebattery storage60approved, not builtupdated Jul 2025Jul 2023granted Dec 2024Jul 2025
E/o the Academy Of Light, Sunderland Road Solar Farmsolar farmsolar farm40application submitted may be out of dateupdated Jul 2024Jul 2024—Jul 2024
Port of Tynebattery storagebattery storage35operationalupdated May 2019Sep 2016—May 2019
A&P Tynewind turbinewind turbine2permission expiredupdated Jun 2015Feb 2008granted Apr 2009Jun 2015
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Viking Energy Network, Blackett Street - Turbine Repoweringwind turbinewind turbine0.8application submittedupdated May 2026Apr 2026—May 2026
Merchant House Warehouse, Tyne Dock Solar Photovoltaics Equipmentrooftop solarrooftop solar0.7approved, not builtupdated Dec 2023Sep 2023granted Nov 2023Dec 2023
Middlefields Depot, Middlefields Industrial Estaterooftop solarrooftop solar0.5approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026
Clarendon, Windmill Wayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026Sep 2025granted Oct 2025Jan 2026
Simonside Industrial Unit, Shaftesbury Avenuerooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Sep 2024granted Oct 2024Oct 2024
Mortimer community college, Reading Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026
Hebburn Lakes Primary School, Campbell Park Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026
Westoe Crown Primary School, Sea Winnings Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026
Dunes Amusement Arcade, Sea Roadrooftop solarrooftop solar0.1approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026
Port Of Tyne, Tyne Dockbattery storagebattery storage—application submitted may be out of dateupdated Aug 2022Jul 2022—Aug 2022
AESC UK, Giga Factories, Plot 2 - Plant 3, Warehouse, Office & Sub-stationsbattery storagebattery storage—approved, not builtupdated May 2026Apr 2024granted Apr 2026May 2026
UTS Engineering, Pilgrimswayrooftop solarrooftop solar—approved, not builtupdated Jan 2026Sep 2025granted Oct 2025Jan 2026

Postcode districts in South Tyneside

DistrictProjects within 10 kmPendingApprovedOperational
NE311149897
NE321059817
NE33655496
NE34715536
NE35907687
NE36826646

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to South Tyneside by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.