Low Horton (50 MW battery storage)

Low Horton is a 50 MW battery storage project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 January 2025, not yet built; the record was last updated on 20 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
20 January 2025record last updated
Northumberlandcouncil area

Planning timeline

DateStage
8 August 2024Application submitted
10 January 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
20 January 2025
Operator or applicant
Bluefield Renewable Developments Limited
Planning authority
Northumberland
Planning application reference
24/02605/RENE
Address (REPD)
S/O A1061 & W/O A192, Cramlington
Council area (by location)
Northumberland
Time to decision
22 weeks
Name in REPD
Low Horton - Battery Energy Storage System
REPD reference
15753

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aesica Pharmaceuticalswind farm6refused0.6
Low Horton Farm Solar Farmsolar farm50approved, not built2.9
Broadway House Farm Solar Farmsolar farm50approved, not built4.1
Seghill Household Waste Recovery Centre -Solar Panelssolar farm5.8application submitted4.2
Seghill Household Waste Recovery Centresolar farm5.8application submitted4.2
Backworth Lane, Backworth Solar Farmsolar farm28approved, not built5.4
Burnt House Farm Solar Farmsolar farm50approved, not built6.7
Burnt House Farm, Nedderton Villagebattery storage50application submitted6.7
Benton Lane, Quorum Business Parksolar farm8application submitted7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0876, -1.5854).