Solar, wind and battery projects near Cramlington (NE23)
61 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE23 (Northumberland): 8 are waiting for a planning decision, 44 approved but not yet running, 5 operational. The largest live scheme is High Brockland Farm, Brock Lane (70 MW battery storage, approved on 7 January 2026, not yet built), 8.7 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 17.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE23
Projects of 1 MW and more (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Aesica Pharmaceuticalswind farm | wind farm | 6 | refusedupdated Apr 2011 | May 2006 | refused Feb 2007 | Apr 2011 | Northumberland | 0.3 |
| Low Hortonbattery storage | battery storage | 50 | approved, not builtupdated Jan 2025 | Aug 2024 | granted Jan 2025 | Jan 2025 | Northumberland | 0.8 |
| Renolit Cramlington Limited, Station Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | Northumberland | 2.0 |
| MSD Cramlingtonwind farm | wind farm | 4 | operationalupdated Feb 2011 | Dec 2006 | granted Jul 2008 | Feb 2011 | Northumberland | 3.5 |
| Low Horton Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Sep 2021 | Apr 2022 | granted Nov 2022 | Sep 2021 | Northumberland | 3.6 |
| Seghill Household Waste Recovery Centre -Solar Panelssolar farm | solar farm | 5.8 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Northumberland | 3.6 |
| Seghill Household Waste Recovery Centresolar farm | solar farm | 5.8 | application submittedupdated Feb 2026 | Dec 2025 | — | Feb 2026 | Northumberland | 3.6 |
| Mylord Crescent, Camperdown Industrial Estate, Unit 12rooftop solar | rooftop solar | 1.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | North Tyneside | 4.1 |
| Backworth Lane, Backworth Solar Farmsolar farm | solar farm | 28 | approved, not built may be out of dateupdated Oct 2024 | Nov 2022 | granted May 2023 | Oct 2024 | North Tyneside | 4.6 |
| Broadway House Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Nov 2025 | Jun 2023 | granted Nov 2023 | Nov 2025 | Northumberland | 5.0 |
| Benton Lane, Quorum Business Parksolar farm | solar farm | 8 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Tyneside | 6.5 |
| Blyth Sewage Treatment Workssolar farm | solar farm | 2.3 | operationalupdated Aug 2023 | Nov 2020 | granted Jan 2021 | Aug 2023 | Northumberland | 6.5 |
| Land East of Mount Pleasant Farmwind turbine | wind turbine | 1.5 | application withdrawnupdated Jul 2015 | Mar 2015 | — | Jul 2015 | Northumberland | 7.0 |
| Burnt House Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated May 2025 | Apr 2022 | granted Nov 2022 | May 2025 | Northumberland | 7.4 |
| Burnt House Farm, Nedderton Villagebattery storage | battery storage | 50 | application submittedupdated Apr 2025 | Apr 2025 | — | Apr 2025 | Northumberland | 7.4 |
| Blyth Harbour Wind Farmwind farm | wind farm | 2.7 | operationalupdated Oct 2013 | May 1991 | granted Mar 1992 | Oct 2013 | Northumberland | 7.6 |
| Blyth Harbour Wind Farm (re-power)wind turbine | wind turbine | 3.4 | operationalupdated Dec 2014 | Jul 2007 | granted Jul 2008 | Dec 2014 | Northumberland | 7.7 |
| Tynemouth Energy Storage System (TESS)battery storage | battery storage | 25 | operationalupdated Aug 2018 | Sep 2016 | — | Aug 2018 | North Tyneside | 8.0 |
| High Brockland Farm, Brock Lanebattery storage | battery storage | 70 | approved, not builtupdated Jan 2026 | May 2025 | granted Jan 2026 | Jan 2026 | Northumberland | 8.7 |
| Newcastle International Airport Phase 3- Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 8.7 |
| Newcastle International Airport Phase 2 Solar Farmsolar farm | solar farm | 4 | approved, not built may be out of dateupdated Oct 2021 | Sep 2021 | granted Feb 2022 | Oct 2021 | Newcastle upon Tyne | 8.7 |
| Newcastle International Airport Phase 4 Solar Farmsolar farm | solar farm | 4 | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 8.7 |
| Newcastle International Airport Phase 1 -Solar Farmsolar farm | solar farm | 3 | under constructionupdated Oct 2021 | Sep 2021 | granted Mar 2022 | Oct 2021 | Newcastle upon Tyne | 8.7 |
| West Sleekburn Battery Storage Compoundbattery storage | battery storage | 30 | approved, not built may be out of dateupdated Feb 2024 | Jun 2022 | granted Oct 2022 | Feb 2024 | Northumberland | 9.0 |
Smaller schemes under 1 MW, mostly rooftop solar (37)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sterling Pharma Solutionsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | North Tyneside | 2.1 |
| Bassington Industrial Estatebattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jun 2025 | Aug 2025 | Northumberland | 2.2 |
| Browns 2000, Colbourne Avenuerooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2023 | Jan 2023 | granted Mar 2023 | Jul 2023 | Northumberland | 2.3 |
| Advanced Composite Engineering, Colbourne Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Northumberland | 2.3 |
| American Air Filter, Bassington Lanerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Northumberland | 2.4 |
| Moorland Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Northumberland | 2.4 |
| North Gosforth Academy, Dudley Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | North Tyneside | 3.3 |
| Seghill Household Waste Recovery Centrebattery storage | battery storage | — | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Northumberland | 3.6 |
| Seghill Household Waste Recovery Centrebattery storage | battery storage | — | application submittedupdated Feb 2026 | Dec 2025 | — | Feb 2026 | Northumberland | 3.6 |
| Broadway House Farm Solar Farmbattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Jun 2023 | granted Nov 2023 | Nov 2025 | Northumberland | 5.0 |
| Blyth Academy, Chase Farm Driverooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Northumberland | 5.2 |
| Planet Place, Stephenson Industrial Estate - Unit 27 - Battery Energy Storagebattery storage | battery storage | — | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | North Tyneside | 5.8 |
| Bede Academy North, Sixth Avenuerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Northumberland | 5.8 |
| Factory C, Coniston Road - Roof repairs & PV Arrayrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Aug 2023 | Jun 2023 | — | Aug 2023 | Northumberland | 6.4 |
| Brunton First School, Roseden Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 6.6 |
| Whitley Road, Holystonebattery storage | battery storage | — | application withdrawnupdated Jun 2026 | Aug 2022 | — | Jun 2026 | North Tyneside | 6.7 |
| Quorum Building, Benton Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | North Tyneside | 6.8 |
| East Sleekburn Wind Farmwind farm | wind farm | — | approved, not builtupdated Dec 2024 | Nov 2023 | granted Nov 2024 | Dec 2024 | Northumberland | 7.3 |
| Gosforth Academyrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Newcastle upon Tyne | 7.9 |
| Gosforth Academy, Knightsbridgerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Sep 2023 | Oct 2023 | Newcastle upon Tyne | 7.9 |
| Grange First School, Norham Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 7.9 |
| YHN House, Benton Park Road- Solar Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Dec 2021 | Jan 2022 | Newcastle upon Tyne | 8.0 |
| Tynemouth Substationbattery storage | battery storage | — | application withdrawnupdated May 2026 | Aug 2024 | — | May 2026 | North Tyneside | 8.1 |
| Unit A, Merlin Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Tyneside | 8.3 |
| Corchester Walk Solar Photovoltaic Panels & Air Sourced Heat Pumpsrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted May 2022 | Jan 2022 | Newcastle upon Tyne | 8.4 |
| Unit C, Merlin Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Tyneside | 8.4 |
| Unit B, Merlin Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | North Tyneside | 8.4 |
| Welford Day Centre, Jubilee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Aug 2023 | Oct 2023 | Newcastle upon Tyne | 8.5 |
| Newcastle International Airport Phase 2battery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 8.7 |
| Newcastle International Airport Phase 3battery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 8.7 |
| Newcastle International Airport Phase 4battery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted Feb 2022 | May 2022 | Newcastle upon Tyne | 8.7 |
| Saint Nicholas Hospital, Jubilee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle upon Tyne | 8.8 |
| David Lloyd Leisure, Castles Farm Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Newcastle upon Tyne | 8.8 |
| The Kenton Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Dec 2023 | granted May 2024 | May 2024 | Newcastle upon Tyne | 9.4 |
| North Tyneside General Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | North Tyneside | 9.6 |
| Armadillo Self Storage, Heatonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Newcastle upon Tyne | 9.7 |
| Ravenswood Primary School, Ravenswood Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 9.9 |
Distance from the average position of the NE23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 3 | 8 | 1 | 0 | 214 |
| Rooftop solar | 28 | 1 | 27 | 0 | 0 | 12.4 |
| Wind farm | 4 | 0 | 1 | 2 | 1 | 0 |
| Wind turbine | 2 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 15 | 4 | 8 | 1 | 0 | 200 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 17.0 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 17.0 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Northumberland decides solar, wind and battery applications
| Applications | Northumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 82 | 10,236 |
| Refused | 31 (38%) | 19% |
| Solar refused | 3 of 36 | 12% |
| Onshore wind refused | 25 of 34 | 45% |
| Battery storage refused | 3 of 12 | 16% |
| Median time from submission to decision | 33.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
All projects in Northumberland
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE23, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.