Energy Projects Near You

Burnt House Farm Solar Farm (50 MW)

Burnt House Farm Solar Farm is a 50 MW solar farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 November 2022, not yet built; the record was last updated on 7 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtstatus in REPD
7 May 2025record last updated
Northumberlandcouncil area

Planning timeline

DateStage
22 April 2022Application submitted
4 November 2022Planning permission granted
4 November 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
7 May 2025
Operator or applicant
Bluefield Renewable Developments Limited
Planning authority
Northumberland
Planning application reference
22/01082/RENE
Site area
76.2 ha
Address (REPD)
Adj To Burnt House Farm, Netherton Village, Bedlington
Council area (by location)
Northumberland
Time to decision
28 weeks
Contracts for Difference
AR5
Name in REPD
Burnt House Farm - Solar Farm
REPD reference
9739

Recorded together with Burnt House Farm, Nedderton Village (50 MW battery storage, application submitted).

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Broadway House Farm Solar Farmsolar farm50approved, not built3.1
Tranwell Airfield Wind Farmwind farm8refused4.8
High Brockland Farm, Brock Lanebattery storage70approved, not built5.4
Low Horton Farm Solar Farmsolar farm50approved, not built5.6
West Sleekburn Battery Storage Compoundbattery storage30approved, not built5.9
Low Hortonbattery storage50approved, not built6.7
Aesica Pharmaceuticalswind farm6refused7.2
Lynemouth Windfarm (Resubmission)wind farm26operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.141, -1.6327).