Energy Projects Near You

Lynemouth Windfarm (Resubmission) (26 MW)

Lynemouth Windfarm (Resubmission) is a 26 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 April 2012; the record was last updated on 24 April 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWwind farm
operationalstatus in REPD
24 April 2012record last updated
Northumberlandcouncil area

Planning timeline

DateStage
20 November 2006Application submitted
11 May 2007Refused by the planning authority
8 January 2009Planning permission granted
8 January 2009Appeal allowed
1 July 2010Construction started
12 April 2012Operational

Project details

Technology
wind farm
Capacity
26 MW
Status (REPD)
operational
Record last updated
24 April 2012
Operator or applicant
Scottish Power Renewables
Planning authority
Northumberland
Planning application reference
CM/20060984
Turbines
13
Address (REPD)
Land adjacent to Rio Tinto Alcan Smelter, Lynemouth (2km north of Ashington)
Council area (by location)
Northumberland
Time to decision
111 weeks
REPD reference
3752

Earlier applications for this site

ApplicationMWSubmittedOutcome
Lynemouth Windfarm CM/200608772.413 October 2006refused 30 May 2007

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Sleekburn Battery Storage Compoundbattery storage30approved, not built4.9
High Brockland Farm, Brock Lanebattery storage70approved, not built5.1
Sisterswind farm8.2operational7.3
North Steads Wind Farmwind farm18.4operational8.9
Burnt House Farm, Nedderton Villagebattery storage50application submitted9.0
Burnt House Farm Solar Farmsolar farm50approved, not built9.0
Broadway House Farm Solar Farmsolar farm50approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2016, -1.5396).