Energy Projects Near You

West Sleekburn Battery Storage Compound (30 MW)

West Sleekburn Battery Storage Compound is a 30 MW battery storage project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 October 2022, not yet built; the record was last updated on 13 February 2024. REPD also records that the planning permission expired on 19 October 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtmay be out of datestatus in REPD
13 February 2024record last updated
Northumberlandcouncil area

REPD also records that the planning permission expired on 19 October 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
21 June 2022Application submitted
19 October 2022Planning permission granted
19 October 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
13 February 2024
Operator or applicant
Enviromena Asset Management UK Limited
Planning authority
Northumberland
Planning application reference
22/01725/FUL
Address (REPD)
West Sleekburn, Bedlington
Council area (by location)
Northumberland
Time to decision
17 weeks
Name in REPD
West Sleekburn - Battery Storage Compound
REPD reference
10957

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Brockland Farm, Brock Lanebattery storage70approved, not built0.6
Broadway House Farm Solar Farmsolar farm50approved, not built4.8
Lynemouth Windfarm (Resubmission)wind farm26operational4.9
Low Horton Farm Solar Farmsolar farm50approved, not built5.4
Burnt House Farm Solar Farmsolar farm50approved, not built5.9
Burnt House Farm, Nedderton Villagebattery storage50application submitted5.9
Low Hortonbattery storage50approved, not built8.2
Aesica Pharmaceuticalswind farm6refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1576, -1.5441).