Solar, wind and battery projects near Ashington (NE63)
30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE63 (Northumberland): 2 are waiting for a planning decision, 17 approved but not yet running, 9 operational. The largest live scheme is High Brockland Farm, Brock Lane (70 MW battery storage, approved on 7 January 2026, not yet built), 2.6 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 12.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE63
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| High Brockland Farm, Brock Lanebattery storage | battery storage | 70 | approved, not builtupdated Jan 2026 | May 2025 | granted Jan 2026 | Jan 2026 | Northumberland | 2.6 |
| West Sleekburn Battery Storage Compoundbattery storage | battery storage | 30 | approved, not built may be out of dateupdated Feb 2024 | Jun 2022 | granted Oct 2022 | Feb 2024 | Northumberland | 2.6 |
| New Moor Shaftsolar farm | solar farm | 4.2 | abandonedupdated Jun 2018 | Jul 2015 | granted Sep 2015 | Jun 2018 | Northumberland | 2.8 |
| Lynemouth Windfarm (Resubmission)wind farm | wind farm | 26 | operationalupdated Apr 2012 | Nov 2006 | granted Jan 2009 | Apr 2012 | Northumberland | 3.0 |
| Ellington South Site, Lynemouth Solar Arraysolar farm | solar farm | 1.2 | approved, not built may be out of dateupdated May 2021 | Apr 2021 | granted Mar 2023 | May 2021 | Northumberland | 4.0 |
| Bewick Driftwind turbine | wind turbine | 2.3 | operationalupdated May 2013 | Oct 2006 | granted Feb 2008 | May 2013 | Northumberland | 4.1 |
| Land East of Mount Pleasant Farmwind turbine | wind turbine | 1.5 | application withdrawnupdated Jul 2015 | Mar 2015 | — | Jul 2015 | Northumberland | 4.8 |
| Blyth Sewage Treatment Workssolar farm | solar farm | 2.3 | operationalupdated Aug 2023 | Nov 2020 | granted Jan 2021 | Aug 2023 | Northumberland | 5.3 |
| Burnt House Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated May 2025 | Apr 2022 | granted Nov 2022 | May 2025 | Northumberland | 6.1 |
| Burnt House Farm, Nedderton Villagebattery storage | battery storage | 50 | application submittedupdated Apr 2025 | Apr 2025 | — | Apr 2025 | Northumberland | 6.1 |
| Broadway House Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Nov 2025 | Jun 2023 | granted Nov 2023 | Nov 2025 | Northumberland | 6.3 |
| Blyth Harbour Wind Farm (re-power)wind turbine | wind turbine | 3.4 | operationalupdated Dec 2014 | Jul 2007 | granted Jul 2008 | Dec 2014 | Northumberland | 6.8 |
| Blyth Harbour Wind Farmwind farm | wind farm | 2.7 | operationalupdated Oct 2013 | May 1991 | granted Mar 1992 | Oct 2013 | Northumberland | 7.3 |
| Low Horton Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Sep 2021 | Apr 2022 | granted Nov 2022 | Sep 2021 | Northumberland | 7.6 |
| Sisterswind farm | wind farm | 8.2 | operationalupdated Oct 2016 | Sep 2011 | granted Feb 2013 | Oct 2016 | Northumberland | 8.7 |
| MSD Cramlingtonwind farm | wind farm | 4 | operationalupdated Feb 2011 | Dec 2006 | granted Jul 2008 | Feb 2011 | Northumberland | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ashington Leisure Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Northumberland | 0.9 |
| Lynx Precast, Lynefield Parkrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Northumberland | 2.9 |
| East Sleekburn Wind Farmwind farm | wind farm | — | approved, not builtupdated Dec 2024 | Nov 2023 | granted Nov 2024 | Dec 2024 | Northumberland | 3.9 |
| Factory C, Coniston Road - Roof repairs & PV Arrayrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Aug 2023 | Jun 2023 | — | Aug 2023 | Northumberland | 5.2 |
| Broadway House Farm Solar Farmbattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Jun 2023 | granted Nov 2023 | Nov 2025 | Northumberland | 6.3 |
| Blyth Academy, Chase Farm Driverooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Northumberland | 6.3 |
| Bede Academy North, Sixth Avenuerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Northumberland | 7.2 |
| County Hall, Loansdeansolar farm | solar farm | 0.8 | operationalupdated Aug 2023 | Dec 2022 | granted Feb 2023 | Aug 2023 | Northumberland | 8.1 |
| County Hall, Loansdeanbattery storage | battery storage | 0.4 | operationalupdated Aug 2023 | Dec 2022 | — | Aug 2023 | Northumberland | 8.1 |
| King Edward Vi School, Cottingwood Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Northumberland | 8.3 |
| Advanced Composite Engineering, Colbourne Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Northumberland | 9.4 |
| Browns 2000, Colbourne Avenuerooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2023 | Jan 2023 | granted Mar 2023 | Jul 2023 | Northumberland | 9.4 |
| Moorland Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Northumberland | 9.5 |
| Northgate Hospital, Adult Autism Unitrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Northumberland | 9.5 |
Distance from the average position of the NE63 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 4 | 2 | 0 | 151 |
| Rooftop solar | 10 | 1 | 9 | 0 | 0 | 3.8 |
| Wind farm | 5 | 0 | 1 | 4 | 0 | 0 |
| Wind turbine | 3 | 0 | 0 | 2 | 0 | 0 |
| Battery storage | 5 | 1 | 3 | 1 | 0 | 150 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 12.6 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 12.6 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Northumberland decides solar, wind and battery applications
| Applications | Northumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 82 | 10,236 |
| Refused | 31 (38%) | 19% |
| Solar refused | 3 of 36 | 12% |
| Onshore wind refused | 25 of 34 | 45% |
| Battery storage refused | 3 of 12 | 16% |
| Median time from submission to decision | 33.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
All projects in Northumberland
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE63, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.