Solar, wind and battery projects near Morpeth (NE61)
23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE61 (Northumberland): 1 is waiting for a planning decision, 12 approved but not yet running, 6 operational. The largest live scheme is High Brockland Farm, Brock Lane (70 MW battery storage, approved on 7 January 2026, not yet built), 8.8 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 20.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE61
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Piramal Healthcare, Whalton Road Solar Farmsolar farm | solar farm | 4.3 | approved, not builtupdated Sep 2025 | Nov 2023 | granted Jun 2024 | Sep 2025 | Northumberland | 3.5 |
| Tranwell Airfield Wind Farmwind farm | wind farm | 8 | refusedupdated Jan 2014 | Dec 2012 | refused Jan 2014 | Jan 2014 | Northumberland | 4.9 |
| Todd Hill Wind Farmwind farm | wind farm | 10 | refusedupdated Feb 2011 | Dec 2008 | refused Jun 2010 | Feb 2011 | Northumberland | 4.9 |
| Burnt House Farm, Nedderton Villagebattery storage | battery storage | 50 | application submittedupdated Apr 2025 | Apr 2025 | — | Apr 2025 | Northumberland | 5.4 |
| Burnt House Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated May 2025 | Apr 2022 | granted Nov 2022 | May 2025 | Northumberland | 5.4 |
| Fenrother Wind Farmwind farm | wind farm | 15 | refused on appealupdated Aug 2014 | Aug 2012 | refused Jan 2013 | Aug 2014 | Northumberland | 6.2 |
| New Moor Shaftsolar farm | solar farm | 4.2 | abandonedupdated Jun 2018 | Jul 2015 | granted Sep 2015 | Jun 2018 | Northumberland | 6.8 |
| Broadway House Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Nov 2025 | Jun 2023 | granted Nov 2023 | Nov 2025 | Northumberland | 8.4 |
| High Brockland Farm, Brock Lanebattery storage | battery storage | 70 | approved, not builtupdated Jan 2026 | May 2025 | granted Jan 2026 | Jan 2026 | Northumberland | 8.8 |
| Sisterswind farm | wind farm | 8.2 | operationalupdated Oct 2016 | Sep 2011 | granted Feb 2013 | Oct 2016 | Northumberland | 9.0 |
| Bewick Driftwind turbine | wind turbine | 2.3 | operationalupdated May 2013 | Oct 2006 | granted Feb 2008 | May 2013 | Northumberland | 9.1 |
| MSD Cramlingtonwind farm | wind farm | 4 | operationalupdated Feb 2011 | Dec 2006 | granted Jul 2008 | Feb 2011 | Northumberland | 9.3 |
| West Sleekburn Battery Storage Compoundbattery storage | battery storage | 30 | approved, not built may be out of dateupdated Feb 2024 | Jun 2022 | granted Oct 2022 | Feb 2024 | Northumberland | 9.3 |
| Lynemouth Windfarm (Resubmission)wind farm | wind farm | 26 | operationalupdated Apr 2012 | Nov 2006 | granted Jan 2009 | Apr 2012 | Northumberland | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| King Edward Vi School, Cottingwood Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Northumberland | 0.6 |
| Northgate Hospital, Adult Autism Unitrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Northumberland | 1.8 |
| County Hall, Loansdeansolar farm | solar farm | 0.8 | operationalupdated Aug 2023 | Dec 2022 | granted Feb 2023 | Aug 2023 | Northumberland | 2.8 |
| County Hall, Loansdeanbattery storage | battery storage | 0.4 | operationalupdated Aug 2023 | Dec 2022 | — | Aug 2023 | Northumberland | 2.8 |
| Dobbies Garden Centre, Heighley Gaterooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | Northumberland | 3.4 |
| Ashington Leisure Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Northumberland | 7.5 |
| Broadway House Farm Solar Farmbattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Jun 2023 | granted Nov 2023 | Nov 2025 | Northumberland | 8.4 |
| East Sleekburn Wind Farmwind farm | wind farm | — | approved, not builtupdated Dec 2024 | Nov 2023 | granted Nov 2024 | Dec 2024 | Northumberland | 9.3 |
| Lynx Precast, Lynefield Parkrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Northumberland | 9.8 |
Distance from the average position of the NE61 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 0 | 3 | 1 | 0 | 104 |
| Rooftop solar | 5 | 0 | 5 | 0 | 0 | 1.5 |
| Wind farm | 7 | 0 | 1 | 3 | 3 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 5 | 1 | 3 | 1 | 0 | 150 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 20.5 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 20.5 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Northumberland decides solar, wind and battery applications
| Applications | Northumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 82 | 10,236 |
| Refused | 31 (38%) | 19% |
| Solar refused | 3 of 36 | 12% |
| Onshore wind refused | 25 of 34 | 45% |
| Battery storage refused | 3 of 12 | 16% |
| Median time from submission to decision | 33.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
All projects in Northumberland
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE61, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.