Tranwell Airfield Wind Farm (8 MW)

Tranwell Airfield Wind Farm is an 8 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 January 2014; the record was last updated on 30 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
refusedstatus in REPD
30 January 2014record last updated
Northumberlandcouncil area

Planning timeline

DateStage
12 December 2012Application submitted
30 January 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
refused
Record last updated
30 January 2014
Operator or applicant
Wind Ventures
Planning authority
Northumberland
Planning application reference
12/03731/RENEIA
Turbines
4
Address (REPD)
Tranwell Airfield, Morpeth
Council area (by location)
Northumberland
Time to decision
59 weeks
REPD reference
3869

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burnt House Farm, Nedderton Villagebattery storage50application submitted4.8
Burnt House Farm Solar Farmsolar farm50approved, not built4.8
Todd Hill Wind Farmwind farm10refused7.3
Broadway House Farm Solar Farmsolar farm50approved, not built7.4
Low Hortonbattery storage50approved, not built9.5
Low Horton Farm Solar Farmsolar farm50approved, not built9.6
Aesica Pharmaceuticalswind farm6refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.136, -1.7079).