Aesica Pharmaceuticals (6 MW wind farm)
Aesica Pharmaceuticals is a 6 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 February 2007; the record was last updated on 27 April 2011.
6 MWwind farm
refusedstatus in REPD
27 April 2011record last updated
Northumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 May 2006 | Application submitted |
| 1 February 2007 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 6 MW
- Status (REPD)
- refused
- Record last updated
- 27 April 2011
- Operator or applicant
- Aesica Pharmaceuticals
- Planning authority
- Northumberland
- Planning application reference
- B/06/00384/RES
- Turbines
- 2
- Address (REPD)
- Cramlington,
- Council area (by location)
- Northumberland
- Time to decision
- 37 weeks
- REPD reference
- 2930
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Aesica Pharmaceuticals Limited 06/00275/FUL | 6 | 22 May 2006 | refused 25 August 2006 |
Who decides
| Applications | Northumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 82 | 10,236 |
| Refused | 31 (38%) | 19% |
| Solar refused | 3 of 36 | 12% |
| Onshore wind refused | 25 of 34 | 45% |
| Battery storage refused | 3 of 12 | 16% |
| Median time from submission to decision | 33.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Low Horton | battery storage | 50 | approved, not built | 0.6 |
| Low Horton Farm Solar Farm | solar farm | 50 | approved, not built | 3.4 |
| Seghill Household Waste Recovery Centre -Solar Panels | solar farm | 5.8 | application submitted | 3.9 |
| Seghill Household Waste Recovery Centre | solar farm | 5.8 | application submitted | 3.9 |
| Broadway House Farm Solar Farm | solar farm | 50 | approved, not built | 4.7 |
| Backworth Lane, Backworth Solar Farm | solar farm | 28 | approved, not built | 4.9 |
| Benton Lane, Quorum Business Park | solar farm | 8 | application submitted | 6.7 |
| Burnt House Farm Solar Farm | solar farm | 50 | approved, not built | 7.2 |
| Burnt House Farm, Nedderton Village | battery storage | 50 | application submitted | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0822, -1.5864).