Sisters (8.2 MW wind farm)

Sisters is an 8.2 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 July 2016; the record was last updated on 3 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWwind farm
operationalstatus in REPD
3 October 2016record last updated
Northumberlandcouncil area

Planning timeline

DateStage
28 September 2011Application submitted
6 February 2013Planning permission granted
27 July 2015Construction started
30 July 2016Operational

Project details

Technology
wind farm
Capacity
8.2 MW
Status (REPD)
operational
Record last updated
3 October 2016
Operator or applicant
Infinis (formerly Novera Energy)
Planning authority
Northumberland
Planning application reference
11/02481/RENEIA
Turbines
4
Address (REPD)
west of Widdrington, approximately 8km north of Ashington, Northumberland
Council area (by location)
Northumberland
Time to decision
71 weeks
REPD reference
4167

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Steads Wind Farmwind farm18.4operational1.7
Fenrother Wind Farmwind farm15refused on appeal7.0
Lynemouth Windfarm (Resubmission)wind farm26operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2499, -1.6182).