Energy Projects Near You

Fenrother Wind Farm (15 MW)

Fenrother Wind Farm is a 15 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 7 August 2014; the record was last updated on 11 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refused on appealstatus in REPD
11 August 2014record last updated
Northumberlandcouncil area

Planning timeline

DateStage
9 August 2012Application submitted
16 January 2013Refused by the planning authority
7 August 2014Appeal refused

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused on appeal
Record last updated
11 August 2014
Operator or applicant
Energiekontor UK
Planning authority
Northumberland
Planning application reference
12/02500/RENEIA
Turbines
5
Council area (by location)
Northumberland
Time to decision
23 weeks
REPD reference
4366

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Todd Hill Wind Farmwind farm10refused4.5
Rayburn Lake Wind Farmwind farm18application withdrawn6.8
Wingates Wind Farmwind farm15operational6.9
Wingates Moor Wind Farmwind farm6refused6.9
Sisterswind farm8.2operational7.0
Rayburn Wind Farmwind farm10refused7.2
North Steads Wind Farmwind farm18.4operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2296, -1.7228).