North Steads Wind Farm (18.4 MW)

North Steads Wind Farm is an 18.4 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 July 2016; the record was last updated on 31 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWwind farm
operationalstatus in REPD
31 October 2016record last updated
Northumberlandcouncil area

Planning timeline

DateStage
30 January 2012Application submitted
6 November 2012Planning permission granted
4 July 2016Operational
20 July 2016Construction started

Project details

Technology
wind farm
Capacity
18.4 MW
Status (REPD)
operational
Record last updated
31 October 2016
Operator or applicant
Ventient (formerly Infinis)
Planning authority
Northumberland
Planning application reference
12/00290/RENEIA
Turbines
9
Address (REPD)
Situated between Widdrington and Red Row to the west of the A1068
Council area (by location)
Northumberland
Time to decision
40 weeks
REPD reference
3905

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sisterswind farm8.2operational1.7
Fenrother Wind Farmwind farm15refused on appeal7.4
Lynemouth Windfarm (Resubmission)wind farm26operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.265, -1.6248).