Energy Projects Near You

Solar, wind and battery projects near Morpeth (NE65)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE65 (Northumberland): 4 approved but not yet running, 2 operational. The largest live scheme is Quotient Sciences, Taylor Drive Solar PV Panel Array (4 MW solar farm, approved on 9 November 2023, not yet built), 9.5 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 29.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
0awaiting a decision
4approved, not running
2operational

Projects within 10 km of NE65

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wingates Wind Farmwind farmwind farm15operationalupdated Jun 2013Dec 2008granted May 2011Jun 2013Northumberland5.6
Wingates Moor Wind Farmwind farmwind farm6refusedupdated Apr 2012Mar 2011refused Mar 2012Apr 2012Northumberland5.6
Debdon Farm Wind Farmwind farmwind farm10.1refusedupdated Jun 2011Jul 2006refused Sep 2006Jun 2011Northumberland7.6
Wandysteadwind farmwind farm3.9refused on appealupdated Jun 2009Jan 2002refused Jun 2002Jun 2009Northumberland8.3
North Steads Wind Farmwind farmwind farm18.4operationalupdated Oct 2016Jan 2012granted Nov 2012Oct 2016Northumberland9.3
Quotient Sciences, Taylor Drive Solar PV Panel Arraysolar farmsolar farm4approved, not builtupdated Nov 2023Oct 2022granted Nov 2023Nov 2023Northumberland9.5
Fenrother Wind Farmwind farmwind farm15refused on appealupdated Aug 2014Aug 2012refused Jan 2013Aug 2014Northumberland9.6
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Chevington Farm, West Chevingtonsolar farmsolar farm0.3approved, not builtupdated May 2025Dec 2023granted Apr 2025May 2025Northumberland8.2
West Chevington Farm, West Chevingtonbattery storagebattery storage—approved, not builtupdated May 2025Dec 2023granted Apr 2025May 2025Northumberland8.2
Quotient Sciences, Taylor Drivebattery storagebattery storage—approved, not builtupdated Nov 2023Oct 2022granted Nov 2023Nov 2023Northumberland9.5

Distance from the average position of the NE65 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm202004.3
Wind farm600240
Battery storage202000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Blyth Offshore Wind Test Site41.5operationalupdated Jul 201829.1
Blyth Offshore Wind Farm Phase 2 Demonstrator Project58.4approved, not builtupdated Apr 202229.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.