Wingates Moor Wind Farm (6 MW)

Wingates Moor Wind Farm is a 6 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 March 2012; the record was last updated on 4 April 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
refusedstatus in REPD
4 April 2012record last updated
Northumberlandcouncil area

Planning timeline

DateStage
17 March 2011Application submitted
22 March 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
refused
Record last updated
4 April 2012
Operator or applicant
BT
Planning authority
Northumberland
Planning application reference
11/00158/RENEIA
Turbines
3
Address (REPD)
Wingates Moor Longframlington Morpeth Northumberland NE65 8RP
Council area (by location)
Northumberland
Time to decision
53 weeks
REPD reference
3462

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wingates Wind Farmwind farm15operational<0.1
Rayburn Lake Wind Farmwind farm18application withdrawn5.4
Rayburn Wind Farmwind farm10refused5.9
Fenrother Wind Farmwind farm15refused on appeal6.9
Debdon Farm Wind Farmwind farm10.1refused7.3
Todd Hill Wind Farmwind farm10refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2753, -1.7964).