Energy Projects Near You

Rayburn Lake Wind Farm (18 MW)

Rayburn Lake Wind Farm is an 18 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 1 November 2011; the record was last updated on 2 December 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
application withdrawnstatus in REPD
2 December 2011record last updated
Northumberlandcouncil area

Planning timeline

DateStage
27 August 2009Application submitted
1 November 2011Application withdrawn

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
application withdrawn
Record last updated
2 December 2011
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Northumberland
Planning application reference
C/09/00154/RENEIA
Turbines
9
Address (REPD)
North East Of Park Head Farm Netherwitton Morpeth Northumberland
Council area (by location)
Northumberland
REPD reference
2740

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rayburn Wind Farmwind farm10refused0.5
Wingates Wind Farmwind farm15operational5.4
Wingates Moor Wind Farmwind farm6refused5.4
Todd Hill Wind Farmwind farm10refused6.0
Fenrother Wind Farmwind farm15refused on appeal6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2304, -1.8301).