Rayburn Lake Wind Farm (18 MW)
Rayburn Lake Wind Farm is an 18 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 1 November 2011; the record was last updated on 2 December 2011.
18 MWwind farm
application withdrawnstatus in REPD
2 December 2011record last updated
Northumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 August 2009 | Application submitted |
| 1 November 2011 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 18 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 2 December 2011
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- Northumberland
- Planning application reference
- C/09/00154/RENEIA
- Turbines
- 9
- Address (REPD)
- North East Of Park Head Farm Netherwitton Morpeth Northumberland
- Council area (by location)
- Northumberland
- REPD reference
- 2740
Who decides
| Applications | Northumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 82 | 10,236 |
| Refused | 31 (38%) | 19% |
| Solar refused | 3 of 36 | 12% |
| Onshore wind refused | 25 of 34 | 45% |
| Battery storage refused | 3 of 12 | 16% |
| Median time from submission to decision | 33.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Rayburn Wind Farm | wind farm | 10 | refused | 0.5 |
| Wingates Wind Farm | wind farm | 15 | operational | 5.4 |
| Wingates Moor Wind Farm | wind farm | 6 | refused | 5.4 |
| Todd Hill Wind Farm | wind farm | 10 | refused | 6.0 |
| Fenrother Wind Farm | wind farm | 15 | refused on appeal | 6.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2304, -1.8301).