Energy Projects Near You

Wingates Wind Farm (15 MW)

Wingates Wind Farm is a 15 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 4 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
4 June 2013record last updated
Northumberlandcouncil area

Planning timeline

DateStage
5 December 2008Application submitted
4 May 2011Planning permission granted
1 August 2012Construction started
31 March 2013Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
4 June 2013
Operator or applicant
Ventient (formerly Infinis)
Planning authority
Northumberland
Planning application reference
C/09/00084/CCMEIA
Turbines
6
Address (REPD)
Wingates, Longhorsley, Morpeth, Northampronshire. NE65 8
Council area (by location)
Northumberland
Time to decision
126 weeks
REPD reference
3754

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wingates Moor Wind Farmwind farm6refused<0.1
Rayburn Lake Wind Farmwind farm18application withdrawn5.4
Rayburn Wind Farmwind farm10refused5.9
Fenrother Wind Farmwind farm15refused on appeal6.9
Debdon Farm Wind Farmwind farm10.1refused7.3
Todd Hill Wind Farmwind farm10refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2753, -1.7964).