Energy Projects Near You

Solar, wind and battery projects near Newbiggin-by-the-Sea (NE64)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE64 (Northumberland): 2 are waiting for a planning decision, 12 approved but not yet running, 6 operational. The largest live scheme is High Brockland Farm, Brock Lane (70 MW battery storage, approved on 7 January 2026, not yet built), 4.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
2awaiting a decision
12approved, not running
6operational

Projects within 10 km of NE64

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lynemouth Windfarm (Resubmission)wind farmwind farm26operationalupdated Apr 2012Nov 2006granted Jan 2009Apr 2012Northumberland2.4
Ellington South Site, Lynemouth Solar Arraysolar farmsolar farm1.2approved, not built may be out of dateupdated May 2021Apr 2021granted Mar 2023May 2021Northumberland2.7
West Sleekburn Battery Storage Compoundbattery storagebattery storage30approved, not built may be out of dateupdated Feb 2024Jun 2022granted Oct 2022Feb 2024Northumberland3.5
High Brockland Farm, Brock Lanebattery storagebattery storage70approved, not builtupdated Jan 2026May 2025granted Jan 2026Jan 2026Northumberland4.0
Bewick Driftwind turbinewind turbine2.3operationalupdated May 2013Oct 2006granted Feb 2008May 2013Northumberland4.3
New Moor Shaftsolar farmsolar farm4.2abandonedupdated Jun 2018Jul 2015granted Sep 2015Jun 2018Northumberland4.7
Land East of Mount Pleasant Farmwind turbinewind turbine1.5application withdrawnupdated Jul 2015Mar 2015—Jul 2015Northumberland5.5
Blyth Sewage Treatment Workssolar farmsolar farm2.3operationalupdated Aug 2023Nov 2020granted Jan 2021Aug 2023Northumberland6.0
Blyth Harbour Wind Farm (re-power)wind turbinewind turbine3.4operationalupdated Dec 2014Jul 2007granted Jul 2008Dec 2014Northumberland6.3
Blyth Harbour Wind Farmwind farmwind farm2.7operationalupdated Oct 2013May 1991granted Mar 1992Oct 2013Northumberland6.7
Broadway House Farm Solar Farmsolar farmsolar farm50approved, not builtupdated Nov 2025Jun 2023granted Nov 2023Nov 2025Northumberland8.3
Low Horton Farm Solar Farmsolar farmsolar farm50approved, not builtupdated Sep 2021Apr 2022granted Nov 2022Sep 2021Northumberland8.8
Burnt House Farm Solar Farmsolar farmsolar farm50approved, not builtupdated May 2025Apr 2022granted Nov 2022May 2025Northumberland8.9
Burnt House Farm, Nedderton Villagebattery storagebattery storage50application submittedupdated Apr 2025Apr 2025—Apr 2025Northumberland8.9
Sisterswind farmwind farm8.2operationalupdated Oct 2016Sep 2011granted Feb 2013Oct 2016Northumberland9.8
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lynx Precast, Lynefield Parkrooftop solarrooftop solar0.5approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Northumberland2.2
Ashington Leisure Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Northumberland3.4
East Sleekburn Wind Farmwind farmwind farm—approved, not builtupdated Dec 2024Nov 2023granted Nov 2024Dec 2024Northumberland5.2
Factory C, Coniston Road - Roof repairs & PV Arrayrooftop solarrooftop solar—application submitted may be out of dateupdated Aug 2023Jun 2023—Aug 2023Northumberland6.1
Blyth Academy, Chase Farm Driverooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Northumberland7.2
Bede Academy North, Sixth Avenuerooftop solarrooftop solar0.5approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Northumberland7.4
Broadway House Farm Solar Farmbattery storagebattery storage—approved, not builtupdated Nov 2025Jun 2023granted Nov 2023Nov 2025Northumberland8.3

Distance from the average position of the NE64 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm60410151
Rooftop solar514001.8
Wind farm401300
Wind turbine300200
Battery storage41300150

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Blyth Offshore Wind Test Site41.5operationalupdated Jul 20189.8
Blyth Offshore Wind Farm Phase 2 Demonstrator Project58.4approved, not builtupdated Apr 20229.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE64, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.