Energy Projects Near You

Highfield Energy Park (40 MW)

Highfield Energy Park is a 40 MW solar farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 August 2025; appeal lodged on 14 January 2026; the record was last updated on 26 January 2026. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
appeal lodgedmay be out of datestatus in REPD
26 January 2026record last updated
Northumberlandcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
30 May 2023Application submitted
12 August 2025Refused by the planning authority
14 January 2026Appeal lodged

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
appeal lodged
Record last updated
26 January 2026
Operator or applicant
Exagen
Planning authority
Northumberland
Planning application reference
23/01717/FUL
Appeal reference
APP/P2935/W/25/3376986
Site area
91.0 ha
Address (REPD)
South West Of Whittonstall
Council area (by location)
Northumberland
Time to decision
115 weeks
REPD reference
12311

The scheme also includes 12.5 MW of battery storage, recorded separately in REPD (appeal lodged).

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kiln Pit Hill Windfarmwind farm12operational1.5
Greenhead Energy Parksolar farm49.9application submitted5.7
Boundary Lanewind farm6operational5.8
Hownsgill Industrial Parksolar farm5under construction7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.898, -1.9022).