Kiln Pit Hill Windfarm (12 MW)

Kiln Pit Hill Windfarm is a 12 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2012; the record was last updated on 25 February 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
25 February 2013record last updated
Northumberlandcouncil area

Planning timeline

DateStage
15 February 2006Application submitted
2 January 2009Planning permission granted
1 November 2011Construction started
1 August 2012Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
25 February 2013
Operator or applicant
Npower Renewables
Planning authority
Northumberland
Planning application reference
20060052
Turbines
6
Address (REPD)
land to the east of A68, approx 1km SE of Kiln Pit Hill
Council area (by location)
Northumberland
Time to decision
150 weeks
REPD reference
3938

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highfield Energy Parksolar farm40appeal lodged1.5
Boundary Lanewind farm6operational4.3
Greenhead Energy Parksolar farm49.9application submitted6.9
Hownsgill Industrial Parksolar farm5under construction7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.886, -1.9144).