Energy Projects Near You

Solar, wind and battery projects near Riding Mill (NE44)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE44 (Northumberland): 2 are waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Highfield Energy Park (40 MW solar farm, refused on 12 August 2025; appeal lodged on 14 January 2026; REPD status may be out of date), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
2awaiting a decision
1approved, not running
1operational

Projects within 10 km of NE44

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Highfield Energy Parksolar farmsolar farm40appeal lodged may be out of dateupdated Jan 2026May 2023refused Aug 2025Jan 2026Northumberland7.0
Highfield Energy Parkbattery storagebattery storage12.5appeal lodged may be out of dateupdated Jan 2026May 2023refused Aug 2025Jan 2026Northumberland7.0
Kiln Pit Hill Windfarmwind farmwind farm12operationalupdated Feb 2013Feb 2006granted Jan 2009Feb 2013Northumberland7.5
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Salem Tubes, Regents Drive Solar PV Equipmentrooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Northumberland9.5

Distance from the average position of the NE44 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1100040
Rooftop solar101000.3
Wind farm100100
Battery storage1100012.5

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE44, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.