Energy Projects Near You

Solar, wind and battery projects near Hexham (NE46)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE46 (Northumberland): 4 are waiting for a planning decision, 3 approved but not yet running. The largest live scheme is Fourstones -Battery Energy Storage (60 MW battery storage, application submitted on 15 August 2025, no decision recorded), 7.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
4awaiting a decision
3approved, not running
0operational

Projects within 10 km of NE46

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fourstones Substation, Fourstones Solar Farm & Battery Energy Storagesolar farmsolar farm32application submittedupdated Jul 2025May 2025—Jul 2025Northumberland5.7
Halfway House, Lincoln Hillbattery storagebattery storage2.5approved, not built may be out of dateupdated Sep 2025Dec 2022granted Jul 2023Sep 2025Northumberland6.6
Halfway House, Lincoln Hillrooftop solarrooftop solar1approved, not built may be out of dateupdated Sep 2025Dec 2022granted Jul 2023Sep 2025Northumberland6.6
Fourstones -Battery Energy Storagebattery storagebattery storage60application submittedupdated Sep 2025Aug 2025—Sep 2025Northumberland7.2
Fourstones Solar Parksolar farmsolar farm49.9application submittedupdated Sep 2025Aug 2025—Sep 2025Northumberland7.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Acomb Village, Acombsolar farmsolar farm1approved, not builtupdated Jan 2026May 2024granted Dec 2025Jan 2026Northumberland1.7
Fourstones Substation, Fourstones Solar Farm & Battery Energy Storagebattery storagebattery storage—application submittedupdated Jul 2025May 2025—Jul 2025Northumberland5.7

Distance from the average position of the NE46 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3210082.9
Rooftop solar101001
Battery storage3210062.5

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE46, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.