Energy Projects Near You

Fourstones Solar Park (49.9 MW)

Fourstones Solar Park is a 49.9 MW solar farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 August 2025, no decision recorded; the record was last updated on 19 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
19 September 2025record last updated
Northumberlandcouncil area

Planning timeline

DateStage
15 August 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
19 September 2025
Operator or applicant
Mespil Solar Energy
Planning authority
Northumberland
Planning application reference
25/02869/RENE
Site area
65.5 ha
Address (REPD)
Fourstones, Hexham
Council area (by location)
Northumberland
Name in REPD
Fourstones - Solar Park
REPD reference
18691

Recorded together with Fourstones -Battery Energy Storage (60 MW battery storage, application submitted).

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fourstones Substation, Fourstones Solar Farm & Battery Energy Storagesolar farm32application submitted1.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0218, -2.1925).