Solar, wind and battery projects near Newcastle upon Tyne (NE17)
26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE17 (Gateshead): 5 are waiting for a planning decision, 12 approved but not yet running, 4 operational. The largest live scheme is Newburn Bridge Road (100 MW battery storage, approved on 31 March 2022, not yet built; REPD status may be out of date), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE17
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Greenhead Energy Parksolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Gateshead | <0.1 |
| Greenhead Energy Parkbattery storage | battery storage | 13 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Gateshead | <0.1 |
| Number One Industrial Estaterooftop solar | rooftop solar | 1 | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | County Durham | 5.5 |
| Highfield Energy Parksolar farm | solar farm | 40 | appeal lodged may be out of dateupdated Jan 2026 | May 2023 | refused Aug 2025 | Jan 2026 | Northumberland | 5.7 |
| Highfield Energy Parkbattery storage | battery storage | 12.5 | appeal lodged may be out of dateupdated Jan 2026 | May 2023 | refused Aug 2025 | Jan 2026 | Northumberland | 5.7 |
| Kiln Pit Hill Windfarmwind farm | wind farm | 12 | operationalupdated Feb 2013 | Feb 2006 | granted Jan 2009 | Feb 2013 | Northumberland | 6.9 |
| Comeleon House Solar PV Farmsolar farm | solar farm | 4 | abandonedupdated Jun 2016 | May 2015 | granted Jun 2015 | Jun 2016 | County Durham | 8.0 |
| Greencroft Estate Turbineswind farm | wind farm | 4 | operationalupdated Jul 2013 | Jun 2011 | granted Nov 2011 | Jul 2013 | County Durham | 8.3 |
| Hownsgill Industrial Parksolar farm | solar farm | 5 | under constructionupdated Jan 2020 | Aug 2015 | granted Mar 2016 | Jan 2020 | County Durham | 8.3 |
| Newburn Bridge Roadbattery storage | battery storage | 100 | approved, not built may be out of dateupdated Oct 2024 | Aug 2021 | granted Mar 2022 | Oct 2024 | Gateshead | 8.5 |
| Green Croft Solar Farmsolar farm | solar farm | 5 | operationalupdated Feb 2017 | Jul 2015 | granted Nov 2015 | Feb 2017 | County Durham | 8.9 |
| Maiden, Annfield Plainbattery storage | battery storage | 38 | approved, not builtupdated Jul 2022 | May 2021 | granted Aug 2021 | Jul 2022 | County Durham | 9.0 |
| Newburn BESSbattery storage | battery storage | 90 | application submitted may be out of dateupdated Jul 2024 | May 2024 | — | Jul 2024 | Newcastle upon Tyne | 9.3 |
| Wagtail Lane, Cragheadsolar farm | solar farm | 27 | refusedupdated Jan 2026 | Jan 2025 | refused Dec 2025 | Jan 2026 | County Durham | 10.0 |
| Land at Derwenthaugh Eco Parkbattery storage | battery storage | 29 | permission expiredupdated May 2020 | Mar 2018 | granted Nov 2018 | May 2020 | Gateshead | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Number One Industrial Estaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Nov 2021 | Dec 2021 | County Durham | 5.5 |
| Harelaw Industrial Estaterooftop solar | rooftop solar | 0.9 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Oct 2023 | Oct 2023 | County Durham | 6.2 |
| Gas Governor Station Solar Systemsolar farm | solar farm | 0.3 | approved, not built may be out of dateupdated Jan 2022 | Nov 2020 | granted Apr 2022 | Jan 2022 | Gateshead | 6.4 |
| Salem Tubes, Regents Drive Solar PV Equipmentrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Northumberland | 6.5 |
| Derwentside Environmental Testing Servs Limitedrooftop solar | rooftop solar | 0.4 | operationalupdated Sep 2024 | May 2024 | granted Sep 2024 | Sep 2024 | County Durham | 6.5 |
| Bailey House, Stargate Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 | Gateshead | 7.2 |
| South Causey Inn, Causey Roadsolar farm | solar farm | 0.2 | refusedupdated Mar 2024 | Sep 2023 | refused Mar 2024 | Mar 2024 | County Durham | 8.9 |
| Warburtons, Shelley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle upon Tyne | 9.2 |
| Shelley Roadbattery storage | battery storage | — | refusedupdated Nov 2018 | Oct 2017 | refused Dec 2017 | Nov 2018 | Newcastle upon Tyne | 9.2 |
| Newburn Haugh Battery Storage Systemcbattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jun 2025 | Jul 2025 | Newcastle upon Tyne | 9.4 |
| Union Hall Road, Lemingtonbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2023 | Aug 2022 | granted Jan 2023 | Feb 2023 | Newcastle upon Tyne | 9.9 |
Distance from the average position of the NE17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 2 | 1 | 2 | 95.2 |
| Rooftop solar | 7 | 0 | 6 | 1 | 0 | 2.9 |
| Wind farm | 2 | 0 | 0 | 2 | 0 | 0 |
| Battery storage | 9 | 3 | 4 | 0 | 1 | 254 |
MW in pipeline: pending, approved and under-construction capacity.
How Gateshead decides solar, wind and battery applications
| Applications | Gateshead | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 1 (4%) | 19% |
| Solar refused | 0 of 20 | 12% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE17, 9 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.