Hownsgill Industrial Park (5 MW solar farm)

Hownsgill Industrial Park is a 5 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 15 February 2019; the record was last updated on 20 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
20 January 2020record last updated
County Durhamcouncil area

Planning timeline

DateStage
28 August 2015Application submitted
1 March 2016Planning permission granted
15 February 2019Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
20 January 2020
Operator or applicant
Project Genesis
Planning authority
County Durham
Planning application reference
DM/15/02364/FPA
Site area
12.0 ha
Address (REPD)
E/o Hownsgill Industrial Park, Knitsley Lane, Consett
Council area (by location)
County Durham
Time to decision
27 weeks
REPD reference
5844

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Boundary Lanewind farm6operational5.6
Green Croft Solar Farmsolar farm5operational6.8
Kiln Pit Hill Windfarmwind farm12operational7.0
Maiden, Annfield Plainbattery storage38approved, not built7.1
Edge Lane, Maiden Law Solar Farm & Battery Storagesolar farm49.9approved, not built7.5
Highfield Energy Parksolar farm40appeal lodged7.6
Greenhead Energy Parksolar farm49.9application submitted8.3
West Durham Wind Farmwind farm24operational8.6
Wagtail Lane, Cragheadsolar farm27refused9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8392, -1.8419).