Energy Projects Near You

Boundary Lane (6 MW wind farm)

Boundary Lane is a 6 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 25 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
County Durhamcouncil area

Planning timeline

DateStage
16 June 2009Application submitted
17 February 2011Planning permission granted
1 September 2012Construction started
31 March 2013Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
25 March 2015
Operator or applicant
EDF
Planning authority
County Durham
Planning application reference
09/00092/CCMEIA
Turbines
3
Address (REPD)
Shotley Quarter, Whittonstall, Nr Consett, Co Durham. DH8 9
Council area (by location)
County Durham
Time to decision
87 weeks
REPD reference
3674

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kiln Pit Hill Windfarmwind farm12operational4.3
Hownsgill Industrial Parksolar farm5under construction5.6
Highfield Energy Parksolar farm40appeal lodged5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8478, -1.9282).