Solar, wind and battery projects near Richmond (DL10)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DL10 (North Yorkshire): 2 are waiting for a planning decision, 9 approved but not yet running, 3 operational. The largest live scheme is Solar Farm at North Of Brompton On Swale (39.3 MW solar farm, approved on 21 August 2025, not yet built), 2.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DL10
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Darlington Road, Skeebysolar farm | solar farm | 55 | operationalupdated Nov 2024 | Oct 2021 | granted Nov 2022 | Nov 2024 | North Yorkshire | 0.6 |
| Land at Stripe Farmsolar farm | solar farm | 5 | operationalupdated Jun 2018 | Jun 2015 | granted Sep 2015 | Jun 2018 | North Yorkshire | 0.7 |
| Darlington Road, Skeebybattery storage | battery storage | 35 | under constructionupdated Mar 2026 | Jun 2023 | granted Aug 2023 | Mar 2026 | North Yorkshire | 1.4 |
| Solar Farm at North Of Brompton On Swalesolar farm | solar farm | 39.3 | approved, not builtupdated Sep 2025 | Feb 2025 | granted Aug 2025 | Sep 2025 | North Yorkshire | 2.8 |
| Middleton Lodge, Kneeton Lanesolar farm | solar farm | 1.3 | application submittedupdated Apr 2026 | Mar 2026 | — | Apr 2026 | North Yorkshire | 5.3 |
| Solar Farm at East Appleton Farmsolar farm | solar farm | 23.5 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 | North Yorkshire | 7.2 |
| Land East of Appleton Farmsolar farm | solar farm | 5 | operationalupdated Jun 2018 | Jun 2015 | granted Sep 2015 | Jun 2018 | North Yorkshire | 7.2 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Brompton Lakes, Easbysolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Aug 2022 | granted Jan 2023 | Jan 2023 | North Yorkshire | 2.3 |
| Foss Way, Walkerville Industrial Estatesolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Mar 2023 | Dec 2022 | granted Jan 2023 | Mar 2023 | North Yorkshire | 4.0 |
| Middleton Lodge, Kneeton Lanerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Mar 2023 | Dec 2022 | granted Feb 2023 | Mar 2023 | North Yorkshire | 5.3 |
| Babcock Land Defence Limited, Dsg Leyburn Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2024 | Jul 2024 | granted Sep 2024 | Dec 2024 | North Yorkshire | 5.3 |
| Cramble Cross Poultry Unit, Back Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | North Yorkshire | 7.8 |
| Cramble Cross Poultry Unit, Back Lanebattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | North Yorkshire | 7.8 |
| Poultry Unit, Park View Farmsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Dec 2022 | Sep 2022 | granted Nov 2022 | Dec 2022 | North Yorkshire | 9.5 |
Distance from the average position of the DL10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 2 | 4 | 3 | 0 | 64.7 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.8 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 35.2 |
MW in pipeline: pending, approved and under-construction capacity.
How North Yorkshire decides solar, wind and battery applications
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
All projects in North Yorkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DL10, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.