Energy Projects Near You

Solar, wind and battery projects near Catterick Garrison (DL9)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DL9 (North Yorkshire): 2 are waiting for a planning decision, 6 approved but not yet running, 3 operational. The largest live scheme is Solar Farm at North Of Brompton On Swale (39.3 MW solar farm, approved on 21 August 2025, not yet built), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
2awaiting a decision
6approved, not running
3operational

Projects within 10 km of DL9

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Farm at North Of Brompton On Swalesolar farmsolar farm39.3approved, not builtupdated Sep 2025Feb 2025granted Aug 2025Sep 2025North Yorkshire3.1
Darlington Road, Skeebybattery storagebattery storage35under constructionupdated Mar 2026Jun 2023granted Aug 2023Mar 2026North Yorkshire3.9
Darlington Road, Skeebysolar farmsolar farm55operationalupdated Nov 2024Oct 2021granted Nov 2022Nov 2024North Yorkshire4.0
Land at Stripe Farmsolar farmsolar farm5operationalupdated Jun 2018Jun 2015granted Sep 2015Jun 2018North Yorkshire4.7
Solar Farm at East Appleton Farmsolar farmsolar farm23.5application submittedupdated Oct 2025Jun 2025—Oct 2025North Yorkshire4.9
Land East of Appleton Farmsolar farmsolar farm5operationalupdated Jun 2018Jun 2015granted Sep 2015Jun 2018North Yorkshire4.9
Middleton Lodge, Kneeton Lanesolar farmsolar farm1.3application submittedupdated Apr 2026Mar 2026—Apr 2026North Yorkshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Babcock Land Defence Limited, Dsg Leyburn Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2024Jul 2024granted Sep 2024Dec 2024North Yorkshire1.6
Foss Way, Walkerville Industrial Estatesolar farmsolar farm0.2approved, not built may be out of dateupdated Mar 2023Dec 2022granted Jan 2023Mar 2023North Yorkshire1.8
Brompton Lakes, Easbysolar farmsolar farm0.2approved, not built may be out of dateupdated Jan 2023Aug 2022granted Jan 2023Jan 2023North Yorkshire2.4
Middleton Lodge, Kneeton Lanerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Mar 2023Dec 2022granted Feb 2023Mar 2023North Yorkshire9.7

Distance from the average position of the DL9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8233064.5
Rooftop solar202000.7
Battery storage1010035

MW in pipeline: pending, approved and under-construction capacity.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DL9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.