Land East of Appleton Farm (5 MW solar farm)

Land East of Appleton Farm is a 5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2016; the record was last updated on 4 June 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 June 2018record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
16 June 2015Application submitted
14 September 2015Planning permission granted
15 January 2016Construction started
27 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 June 2018
Operator or applicant
Gresham House
Planning authority
North Yorkshire
Planning application reference
15/00448/FULL
Address (REPD)
Ld N Of East Appleton Hall Far, East Appleton, Richmond, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
13 weeks
REPD reference
5400

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at East Appleton Farmsolar farm23.5application submitted<0.1
Solar Farm at North Of Brompton On Swalesolar farm39.3approved, not built4.4
South Lowfields Farmsolar farm49.9approved, not built5.2
Darlington Road, Skeebysolar farm55operational7.2
Os Field 6800 Fence Dike Lane Solar Farmsolar farm49.9approved, not built7.4
Land at Stripe Farmsolar farm5operational7.8
Solar Farm at N/O Black Bridge Danby Wiskesolar farm19application submitted9.6
Stell Solar Farmsolar farm30application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3569, -1.6374).