Solar Farm at East Appleton Farm (23.5 MW)

Solar Farm at East Appleton Farm is a 23.5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 24 June 2025, no decision recorded; the record was last updated on 28 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23.5 MWsolar farm
application submittedstatus in REPD
28 October 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
24 June 2025Application submitted

Project details

Technology
solar farm
Capacity
23.5 MW
Status (REPD)
application submitted
Record last updated
28 October 2025
Operator or applicant
Enviromena
Planning authority
North Yorkshire
Planning application reference
ZD25/00369/FULL
Site area
32.6 ha
Address (REPD)
East Appleton Farm, East Appleton, Richmond
Council area (by location)
North Yorkshire
Name in REPD
Tunstall & East Appleton Solar Farm - Solar Farm
REPD reference
19653

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land East of Appleton Farmsolar farm5operational<0.1
Solar Farm at North Of Brompton On Swalesolar farm39.3approved, not built4.4
South Lowfields Farmsolar farm49.9approved, not built5.2
Darlington Road, Skeebysolar farm55operational7.2
Os Field 6800 Fence Dike Lane Solar Farmsolar farm49.9approved, not built7.4
Land at Stripe Farmsolar farm5operational7.8
Solar Farm at N/O Black Bridge Danby Wiskesolar farm19application submitted9.6
Stell Solar Farmsolar farm30application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3569, -1.6375).