Energy Projects Near You

Solar, wind and battery projects near Whitby (YO22)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO22 (North Yorkshire): 1 is waiting for a planning decision, 3 approved but not yet running. The largest live scheme is Whitby Seafoods, Stainsacre Lane Industrial Estate (0.9 MW rooftop solar, approved on 2 July 2025, not yet built), 2.8 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 37.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
1awaiting a decision
3approved, not running
0operational

Projects within 10 km of YO22

Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sainsburys Supermarket, Stainsacre Lanerooftop solarrooftop solar0.3application submitted may be out of dateupdated Oct 2024Jul 2024—Oct 2024North Yorkshire2.6
Sainsburys Supermarket, Stainsacre Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024North Yorkshire2.6
Whitby Seafoods, Stainsacre Lane Industrial Estaterooftop solarrooftop solar0.9approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025North Yorkshire2.8
Whitby Leisure Centre, West Cliff Avenuerooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026North Yorkshire4.3

Distance from the average position of the YO22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar413001.7

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201537.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO22, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.