Land at Sutor Farm (5 MW solar farm)

Land at Sutor Farm is a 5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 21 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
21 June 2016record last updated
Somersetcouncil area

Planning timeline

DateStage
16 October 2014Application submitted
19 March 2015Planning permission granted
20 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
21 June 2016
Operator or applicant
Elgin Energy EsCo
Planning authority
Somerset
Planning application reference
14/05472/FUL
Site area
9.3 ha
Address (REPD)
Land at Sutor Farm, Wincanton
Council area (by location)
Somerset
Time to decision
22 weeks
REPD reference
4916

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brains Solar Farmsolar farm18.8approved, not built0.9
Hook Valley Solar Parksolar farm17operational3.3
Clapton Farm Solar Parksolar farm5operational3.9
Manor Farm (Dorset)solar farm5operational5.6
Land at Bowden Lanesolar farm5operational6.5
Silton Wind Farmwind farm10refused on appeal6.6
Land at Stalbridge Parksolar farm5operational7.1
Higher Farmsolar farm11refused on appeal7.2
Fernbrook Solar farm & Battery storagesolar farm49.9approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0357, -2.3917).