Manor Farm (Dorset) (5 MW solar farm)

Manor Farm (Dorset) is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 June 2014; the record was last updated on 23 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 July 2014record last updated
Dorsetcouncil area

Planning timeline

DateStage
5 August 2013Application submitted
8 November 2013Planning permission granted
30 November 2013Construction started
9 June 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 July 2014
Operator or applicant
INRG Solar
Planning authority
Dorset
Planning application reference
2/2013/0791/PLNG
Site area
16.1 ha
Address (REPD)
Land At Manor Farm E377815 N128359, Gillingham, Dorset
Council area (by location)
Dorset
Time to decision
14 weeks
REPD reference
1904

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Silton Wind Farmwind farm10refused on appeal1.4
Clapton Farm Solar Parksolar farm5operational2.1
Fernbrook Solar farm & Battery storagesolar farm49.9approved, not built5.3
Land at Sutor Farmsolar farm5operational5.6
Brains Solar Farmsolar farm18.8approved, not built5.9
Higher Farmsolar farm11refused on appeal6.6
Hook Valley Solar Parksolar farm17operational8.2
Hawkers Hill Energy Parkbattery storage20operational8.6
Shaftesbury Energy Parkbattery storage100approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0541, -2.3179).