Holwell Hill (6 MW solar farm)

Holwell Hill is a 6 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 May 2016; the record was last updated on 27 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
operationalstatus in REPD
27 May 2016record last updated
Somersetcouncil area

Planning timeline

DateStage
1 August 2014Application submitted
30 January 2015Refused by the planning authority
1 April 2015Appeal lodged
28 August 2015Planning permission granted
28 August 2015Appeal allowed
15 February 2016Construction started
15 May 2016Operational

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
27 May 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Somerset
Planning application reference
2014/1562/FUL
Appeal reference
APP/Q3305/W/15/3007564
Site area
14.0 ha
Address (REPD)
Land At Toid, Burts Hill To Nunney Catch Roundabout, Trudoxhill, Frome, Somerset
Council area (by location)
Somerset
Time to decision
56 weeks
REPD reference
2004

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Sharpshaw Farm solar parksolar farm5.3refused2.6
Monksham Solar Farmsolar farm10.7operational3.7
Court Farm (Frome)solar farm6.8refused on appeal4.6
West Woodlandssolar farm5operational4.6
Selwood Solar Farmsolar farm6application withdrawn5.5
Frome Power, Styles Close Energy Storage Facilitybattery storage30application submitted6.7
Lodge Farm Solar Farmsolar farm5under construction8.5
Ash Farm, Charlton Roadbattery storage10approved, not built8.7
St Georges Cross Farm, Berkley Lanebattery storage60refused8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1983, -2.384).