West Woodlands (5 MW solar farm)

West Woodlands is a 5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 22 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 April 2016record last updated
Somersetcouncil area

Planning timeline

DateStage
20 November 2014Application submitted
24 February 2015Refused by the planning authority
1 April 2015Appeal lodged
24 August 2015Planning permission granted
24 August 2015Appeal allowed
25 November 2015Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 April 2016
Operator or applicant
Sunsave 24/ Vogt solar
Planning authority
Somerset
Planning application reference
2014/2326/FUL
Appeal reference
APP/Q3305/W/15/3006749
Site area
9.9 ha
Address (REPD)
Court Farm, West Woodlands, Frome
Council area (by location)
Somerset
Time to decision
40 weeks
REPD reference
4889

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Court Farm (Frome)solar farm6.8refused on appeal<0.1
Monksham Solar Farmsolar farm10.7operational1.7
Selwood Solar Farmsolar farm6application withdrawn2.5
Little Sharpshaw Farm solar parksolar farm5.3refused2.7
Frome Power, Styles Close Energy Storage Facilitybattery storage30application submitted4.1
Holwell Hillsolar farm6operational4.6
Lodge Hill, Berkley Solar Parksolar farm14.5approved, not built5.6
St Georges Cross Farm, Berkley Lanebattery storage60refused6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1948, -2.3184).