Energy Projects Near You

Lodge Hill, Berkley Solar Park (14.5 MW)

Lodge Hill, Berkley Solar Park is a 14.5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 October 2022, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.5 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
Somersetcouncil area

Planning timeline

DateStage
24 November 2021Application submitted
21 October 2022Planning permission granted
21 October 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
14.5 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Wessex Solar Energy Limited
Planning authority
Somerset
Planning application reference
2021/2191/FUL
Site area
23.3 ha
Address (REPD)
Lodge Hill Berkley Frome
Council area (by location)
Somerset
Time to decision
47 weeks
Contracts for Difference
AR7a
Name in REPD
Lodge Hill, Berkley - Solar Park
REPD reference
6797

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Frome Power, Styles Close Energy Storage Facilitybattery storage30application submitted2.5
St Georges Cross Farm, Berkley Lanebattery storage60refused2.6
Selwood Solar Farmsolar farm6application withdrawn3.5
Storridge Road Solar Farmsolar farm31approved, not built5.4
Court Farm (Frome)solar farm6.8refused on appeal5.6
West Woodlandssolar farm5operational5.6
Bluebell Wood Solar Farm & Battery Storagesolar farm49.9approved, not built5.7
Hoopers Pool, Southwicksolar farm30application submitted6.3
Little Sharpshaw Farm solar parksolar farm5.3refused6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2337, -2.2683).