Energy Projects Near You

Storridge Road Solar Farm (31 MW)

Storridge Road Solar Farm is a 31 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 October 2023, not yet built; the record was last updated on 1 February 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31 MWsolar farm
approved, not builtstatus in REPD
1 February 2022record last updated
Wiltshirecouncil area

Planning timeline

DateStage
29 November 2021Application submitted
12 October 2023Planning permission granted
12 October 2026Permission expired

Project details

Technology
solar farm
Capacity
31 MW
Status (REPD)
approved, not built
Record last updated
1 February 2022
Operator or applicant
NextPower SPV 15 Limited
Planning authority
Wiltshire
Planning application reference
PL/2021/10592
Site area
43.0 ha
Address (REPD)
The west side of Storridge Road, Westbury
Council area (by location)
Wiltshire
Time to decision
97 weeks
Name in REPD
Storridge Road - Solar Farm
REPD reference
10514

Recorded together with Storridge Road (battery storage, approved, not built).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blenches Millsolar farm6.1operational2.0
Land at Poles Hole Farmsolar farm6.8operational2.4
Land West Side of Axe and Cleaver Lanesolar farm5operational2.4
Hoopers Pool, Southwicksolar farm30application submitted2.9
Bluebell Wood Solar Farm & Battery Storagesolar farm49.9approved, not built3.3
St Georges Cross Farm, Berkley Lanebattery storage60refused5.3
Lodge Hill, Berkley Solar Parksolar farm14.5approved, not built5.4
Trowle Commonsolar farm5operational6.3
Cockhill Solar Farmsolar farm20operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2706, -2.2186).