Energy Projects Near You

Cockhill Solar Farm (20 MW)

Cockhill Solar Farm is a 20 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 14 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
operationalstatus in REPD
14 July 2015record last updated
Wiltshirecouncil area

Planning timeline

DateStage
10 June 2014Application submitted
28 August 2014Planning permission granted
15 November 2014Construction started
26 March 2015Operational

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
operational
Record last updated
14 July 2015
Operator or applicant
Next Energy Solar Fund Ltd
Planning authority
Wiltshire
Planning application reference
14/05596/FUL
Site area
42.4 ha
Address (REPD)
Land at Cockhill Farm Cockhill Trowbridge Wiltshire
Council area (by location)
Wiltshire
Time to decision
11 weeks
REPD reference
2343

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trowle Commonsolar farm5operational0.8
Kingston Farmsolar farm5operational2.2
Marsh Farm Hilpertonsolar farm9.1operational2.9
Whaddon Lane, Hilpertonsolar farm25approved, not built3.3
Land West Side of Axe and Cleaver Lanesolar farm5operational4.5
Land at Poles Hole Farmsolar farm6.8operational4.6
Hoopers Pool, Southwicksolar farm30application submitted5.0
Little Chalfield Solar Farmsolar farm12refused on appeal5.4
Bluebell Wood Solar Farm & Battery Storagesolar farm49.9approved, not built5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3315, -2.224).