Marsh Farm Hilperton (9.1 MW solar farm)
Marsh Farm Hilperton is a 9.1 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 March 2015; the record was last updated on 4 September 2018.
9.1 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Wiltshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 January 2014 | Application submitted |
| 30 April 2014 | Planning permission granted |
| 1 December 2014 | Construction started |
| 14 March 2015 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 9.1 MW
- Status (REPD)
- operational
- Record last updated
- 4 September 2018
- Operator or applicant
- Foresight
- Planning authority
- Wiltshire
- Planning application reference
- 14/00592/FUL
- Address (REPD)
- Land North Of Marsh Farm Marsh Road Hilperton Marsh Wiltshire
- Council area (by location)
- Wiltshire
- Time to decision
- 13 weeks
- REPD reference
- 2373
Who decides
| Applications | Wiltshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 140 | 10,236 |
| Refused | 18 (13%) | 19% |
| Solar refused | 13 of 110 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 4 of 29 | 16% |
| Median time from submission to decision | 20.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 7 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Whaddon Lane, Hilperton | solar farm | 25 | approved, not built | 0.6 |
| Cockhill Solar Farm | solar farm | 20 | operational | 2.9 |
| Trowle Common | solar farm | 5 | operational | 3.7 |
| Norrington Gate Farm, Broughton Gifford | battery storage | 150 | approved, not built | 3.8 |
| Kingston Farm | solar farm | 5 | operational | 4.1 |
| Roundponds Farm Solar Park | solar farm | 13.5 | operational | 4.5 |
| Leechpool Farm, Norrington Battery Storage | battery storage | 13 | permission expired | 4.5 |
| Norrington Common Solar Farm | solar farm | 10 | operational | 4.7 |
| Studley Farm Solar Farm & Battery Storage | solar farm | 49.9 | approved, not built | 4.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3422, -2.1856).