Kingston Farm (5 MW solar farm)

Kingston Farm is a 5 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2011; the record was last updated on 8 March 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
8 March 2013record last updated
Wiltshirecouncil area

Planning timeline

DateStage
31 March 2011Application submitted
17 May 2011Planning permission granted
1 July 2011Construction started
1 October 2011Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
8 March 2013
Operator or applicant
BOA Property / AEE Renewables UK
Planning authority
Wiltshire
Planning application reference
W/11/01064/FUL
Address (REPD)
Holt Road, Bradford-on-Avon, Wiltshire
Council area (by location)
Wiltshire
Time to decision
7 weeks
REPD reference
1165

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cockhill Solar Farmsolar farm20operational2.2
Trowle Commonsolar farm5operational2.4
Marsh Farm Hilpertonsolar farm9.1operational4.1
Little Chalfield Solar Farmsolar farm12refused on appeal4.1
Whaddon Lane, Hilpertonsolar farm25approved, not built4.2
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built5.7
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built6.0
Land at Poles Hole Farmsolar farm6.8operational6.3
Hoopers Pool, Southwicksolar farm30application submitted6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3466, -2.2442).